Task Definition
for a Road Building Project
As an example of construction planning, suppose
that we wish to develop a plan for a road construction project including two
culverts. Initially, we divide project activities into three categories as
shown in Figure 1-2: structures, roadway, and general. This division is based
on the major types of design elements to be constructed. Within the roadway
work, a further sub-division is into earthwork and pavement. Within these
subdivisions, we identify clearing, excavation, filling and finishing
(including seeding and sodding) associated with earthwork, and we define
watering, compaction and paving sub-activities associated with pavement.
Finally, we note that the roadway segment is fairly long, and so individual
activities can be defined for different physical segments along the roadway
path. In Figure 9-2, we divide each paving and earthwork activity into
activities specific to each of two roadway segments. For the culvert
construction, we define the sub-divisions of structural excavation, concreting,
and reinforcing. Even more specifically, structural excavation is divided into
excavation itself and the required backfill and compaction. Similarly,
concreting is divided into placing concrete forms, pouring concrete, stripping
forms, and curing the concrete. As a final step in the structural planning,
detailed activities are defined for reinforcing each of the two culverts.
General work activities are defined for move in, general supervision, and clean
up. As a result of this planning, over thirty different detailed activities
have been defined.
At the option of the planner, additional
activities might also be defined for this project. For example, materials
ordering or lane striping might be included as separate activities. It might
also be the case that a planner would define a different hierarchy of work
breakdowns than that shown in Figure 9-2. For example, placing reinforcing
might have been a sub-activity under concreting for culverts. One reason for
separating reinforcement placement might be to emphasize the different material
and resources required for this activity. Also, the division into separate
roadway segments and culverts might have been introduced early in the
hierarchy. With all these potential differences, the important aspect is to
insure that all necessary activities are included somewhere in the final plan.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.