Civil - Construction Planning And Scheduling
Defining Precedence Relationships Among Activities
Once work
activities have been defined, the relationships among the activities can be
specified. Precedence relations between activities signify that the activities
must take place in a particular sequence. Numerous natural sequences exist for
construction activities due to requirements for structural integrity,
regulations, and other technical requirements. For example, design drawings
cannot be checked before they are drawn. Diagramatically, precedence
relationships can be illustrated by a network or graph in which the activities
are represented by arrows as in Figure 9-0. The arrows in Figure 9-3 are called
branches or links in the activity network, while the circles marking the
beginning or end of each arrow are called nodes or events. In this figure, links
represent particular activities, while the nodes represent milestone events.
More complicated precedence relationships can also
be specified. For example, one activity might not be able to start for several
days after the completion of another activity. As a common example, concrete
might have to cure (or set) for several days before formwork is removed. This
restriction on the removal of forms activity is called a lag between the
completion of one activity (i.e., pouring concrete in this case) and the start
of another activity (i.e., removing formwork in this case). Many computer based
scheduling programs permit the use of a variety of precedence relationships.
Three
mistakes should be avoided in specifying predecessor relationships for
construction plans. First, a circle of activity precedences will result in an
impossible plan. For example, if activity A precedes activity B, activity B
precedes activity C, and activity C precedes activity A, then the project can
never be started or completed! Figure 9-4 illustrates the resulting activity network.
Fortunately, formal scheduling methods and good computer scheduling programs
will find any such errors in the logic of the construction plan.
Forgetting
a necessary precedence relationship can be more insidious. For example, suppose
that installation of dry wall should be done prior to floor finishing. Ignoring
this precedence relationship may result in both activities being scheduled at
the same time. Corrections on the spot may result in increased costs or
problems of quality in the completed project. Unfortunately, there are few ways
in which precedence omissions can be found other than with checks by
knowledgeable managers or by comparison to comparable projects. One other
possible but little used mechanism for checking precedences is to conduct a
physical or computer based simulation of the construction process and observe
any problems.
Finally, it is important to realize that different
types of precedence relationships can be defined and that each has different
implications for the schedule of activities:
z Some activities have a necessary technical or
physical relationship that cannot be superseded. For example, concrete pours
cannot proceed before formwork and reinforcement are in place.
z Some activities have a necessary precedence
relationship over a continuous space rather than as discrete work task
relationships. For example, formwork may be placed in the first part of an
excavation trench even as the excavation equipment continues to work further
along in the trench. Formwork placement cannot proceed further than the
excavation, but the two activities can be started and stopped independently
within this constraint.
z Some "precedence relationships" are
not technically necessary but are imposed due to implicit decisions within the
construction plan. For example, two activities may require the same piece of
equipment so a precedence relationship might be defined between the two to
insure that they are not scheduled for the same time period. Which activity is
scheduled first is arbitrary. As a second example, reversing the sequence of
two activities may be technically possible but more expensive. In this case,
the precedence relationship is not physically necessary but only applied to
reduce costs as perceived at the time of scheduling.
In revising schedules as work proceeds, it is
important to realize that different types of precedence relationships have
quite different implications for the flexibility and cost of changing the
construction plan. Unfortunately, many formal scheduling systems do not possess
the capability of indicating this type of flexibility. As a result, the burden
is placed upon the manager of making such decisions and insuring realistic and
effective schedules. With all the other responsibilities of a project manager,
it is no surprise that preparing or revising the formal, computer based
construction plan is a low priority to a manager in such cases. Nevertheless,
formal construction plans may be essential for good management of complicated
projects.
Example
1-4: Precedence Definition for Site Preparation and Foundation Work
Suppose that a site preparation and concrete slab
foundation construction project consists of nine different activities:
A.Site
clearing (of brush and minor debris),
B. Removal
of trees,
C.General
excavation,
D.Grading
general area,
E. Excavation
for utility trenches,
F. Placing
formwork and reinforcement for concrete,
G.Installing
sewer lines,
H. Installing
other utilities, I. Pouring concrete.
Activities A (site clearing) and B (tree removal) do not have
preceding activities since they depend on none of the other activities. We
assume that activities C (general excavation) and D (general grading) are
preceded by activity A (site clearing). It might also be the case that the
planner wished to delay any excavation until trees were removed, so that B
(tree removal) would be a precedent activity to C (general excavation) and D
(general grading). Activities E (trench excavation) and F (concrete preparation)
cannot begin until the completion of general excavation and tree removal, since
they involve subsequent excavation and trench preparation. Activities G
(install lines) and H (install utilities) represent installation in the utility
trenches and cannot be attempted until the trenches are prepared, so that
activity E (trench excavation) is a preceding activity. We also assume that the
utilities should not be installed until grading is completed to avoid equipment
conflicts, so activity D (general grading) is also preceding activities G
(install sewers) and H (install utilities). Finally, activity I (pour concrete)
cannot begin until the sewer line is installed and formwork and reinforcement
are ready, so activities F and G are preceding. Other utilities may be routed
over the slab foundation, so activity H (install utilities) is not necessarily
a preceding activity for activity I (pour concrete). The result of our planning
are the immediate precedences shown in Table 1-1.
With this
information, the next problem is to represent the activities in a network
diagram and to determine all the precedence relationships among the activities.
One network representation of these nine activities is shown in Figure 9-5, in
which the activities appear as branches or links between nodes. The nodes
represent milestones of possible beginning and starting times. This
representation is called an activity-on-branch diagram. Note that an initial
event beginning activity is defined (Node 0 in Figure 9-5), while node 5
represents the completion of all activities.
Alternatively, the nine activities could be
represented by nodes and predecessor relationships by branches or links, as in
Figure 1-6. The result is an activity-on-node diagram. In Figure 9-6, new
activity nodes representing the beginning and the end of construction have been
added to mark these important milestones.
These
network representations of activities can be very helpful in visualizing the
various activities and their relationships for a project. Whether activities
are represented as branches (as in Figure 1-5) or as nodes (as in Figure 1-5)
is largely a matter of organizational or personal choice. Some considerations
in choosing one form or another are discussed in our website.
It is
also notable that Table 1-1 lists only the immediate predecessor relationships.
Clearly, there are other precedence relationships which involve more than one
activity. For example, "installing sewer lines" (activity G) cannot
be undertaken before "site clearing" (Activity A) is complete since
the activity "grading general area" (Activity D) must precede
activity G and must follow activity A. Table 1-1 is an implicit precedence list
since only immediate predecessors are recorded. An explicit predecessor list
would include all of the preceding activities for activity G. Table 1-2 shows
all such predecessor relationships implied by the project plan. This table can
be produced by tracing all paths through the network back from a particular
activity and can be performed algorithmically. For example, inspecting Figure
1-6 reveals that each activity except for activity B depends upon the
completion of activity A.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.