Civil - Construction Planning And Scheduling :
Critical path
for a fabrication project
As another example of critical
path scheduling, consider the seven activities associated with the fabrication
of a steel component. Figure 2-7 shows the network diagram
associated with these seven activities. Note that an additional dummy activity
X has been added to insure that the correct precedence relationships are
maintained for activity E. A simple rule to observe is that if an activity has
more than one immediate predecessor and another activity has at least one but
not all of these predecessor activity as a predecessor, a dummy activity will
be required to maintain precedence relationships. Thus, in the figure, activity
E has activities B and C as predecessors, while activity D has only activity C as
a predecessor. Hence, a dummy activity is required. Node numbers have also been
added to this figure using the procedure outlined. Note that the
node numbers on nodes 1 and 2 could have been exchanged in this numbering
process since after numbering node 0, either node 1 or node 2 could be numbered
next.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.