Home | | Construction Planning and Scheduling | Critical path for a fabrication project

Chapter: Civil : Construction Planning And Scheduling

Critical path for a fabrication project

Critical path for a fabrication project
Civil - Construction Planning And Scheduling : Critical path for a fabrication project - Example

Civil - Construction Planning And Scheduling : 


Critical path for a fabrication project

 

As another example of critical path scheduling, consider the seven activities associated with the fabrication of a steel component. Figure 2-7 shows the network diagram associated with these seven activities. Note that an additional dummy activity X has been added to insure that the correct precedence relationships are maintained for activity E. A simple rule to observe is that if an activity has more than one immediate predecessor and another activity has at least one but not all of these predecessor activity as a predecessor, a dummy activity will be required to maintain precedence relationships. Thus, in the figure, activity E has activities B and C as predecessors, while activity D has only activity C as a predecessor. Hence, a dummy activity is required. Node numbers have also been added to this figure using the procedure outlined. Note that the node numbers on nodes 1 and 2 could have been exchanged in this numbering process since after numbering node 0, either node 1 or node 2 could be numbered next.


Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Construction Planning And Scheduling : Critical path for a fabrication project |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2024 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.