Critical
Path Scheduling for Activity-on-Node and with Leads, Lags, and Windows
Performing the critical path scheduling algorithm for
activity-on-node representations is only a small variation from the
activity-on-branch algorithm presented above. An example of the
activity-on-node diagram for a seven activity network is shown in Figure 10-3.
Some addition terminology is needed to account for the time delay at a node
associated with the task activity. Accordingly, we define: ES(i) as the
earliest start time for activity (and node) i, EF(i) is the earliest finish
time for activity (and node) i, LS(i) is the latest start and LF(i) is the
latest finish time for activity (and node) i. Our website has the relevant
calculations for the node numbering algorithm, the forward pass and the
backward pass calculations.
For manual application of the critical path algorithm shown in Our website, it is helpful to draw a square of four entries, representing the ES(i), EF(i), LS(i) and LF (i) as shown in Figure 10-14. During the forward pass, the boxes for ES(i) and EF(i) are filled in. As an exercise for the reader, the seven activity network in Figure 2-3 can be scheduled. Results should be identical to those obtained for the activity-on-branch calculations.
Building on the
critical path scheduling
calculations described in the previous sections, some additional capabilities are
useful. Desirable extensions include the definition of allowable windows for
activities and the introduction of more complicated precedence relationships
among activities. For example, a planner may wish to have an activity of
removing formwork from a new building component follow the concrete pour by
some pre-defined lag period to allow setting. This delay would represent a
required gap between the completion of a preceding activity and the start of a
successor. The scheduling calculations to accommodate these complications will
be described in this section. Again, the standard critical path scheduling
assumptions of fixed activity durations and unlimited resource availability
will be made here, although these assumptions will be relaxed in later
sections.
A capability of many scheduling programs is to
incorporate types of activity interactions in addition to the straightforward
predecessor finish to successor start constraint used in Section 2.3.
Incorporation of additional categories of interactions is often called
precedence diagramming. For example, it may be the case that installing
concrete forms in a foundation trench might begin a few hours after the start
of the trench excavation. This would be an example of a start-to-start
constraint with a lead: the start of the trench-excavation activity would lead
the start of the concrete-form-placement activity by a few hours. Eight
separate categories of precedence constraints can be defined, representing
greater than (leads) or less than (lags) time constraints for each of four
different inter-activity relationships. These relationships are summarized in Our website -
8. Typical
precedence relationships would be:
z Direct or
finish-to-start leads
The successor activity cannot start until the preceding
activity is complete by at least the prescribed lead time (FS). Thus, the start
of a successor activity must exceed the finish of the preceding activity by at
least FS.
z Start-to-start
leads
The successor activity cannot start until work on the
preceding activity has been underway by at least the prescribed lead time (SS).
z Finish-to-finish
leadss
The successor activity must have at least FF periods of work
remaining at the completion of the preceding activity.
z Start-to-finish
leads
The successor activity must have at least SF periods of work
remaining at the start of the preceding activity.
The computations with these lead and lag constraints
are somewhat more complicated variations on the basic calculations defined in Our website for critical path scheduling. For example, a start-to-start lead
would modify the calculation of the earliest start time to consider whether or
not the necessary lead constraint was met:
(2.12)
where SSij represents a start-to-start lead between
activity (i,j) and any of the activities starting at event j.
The possibility of interrupting or splitting activities into
two work segments can be particularly important to insure feasible schedules in
the case of numerous lead or lag constraints. With activity splitting, an
activity is divided into two sub-activities with a possible gap or idle time
between work on the two sub activities. The computations for scheduling treat
each sub-activity separately after a split is made. Splitting is performed to
reflect available scheduling flexibility or to allow the development of a
feasible schedule. For example, splitting may permit scheduling the early
finish of a successor activity at a date later than the earliest start of the successor
plus its duration. In effect, the successor activity is split into two segments
with the later segment scheduled to finish after a particular time. Most
commonly, this occurs when a constraint involving the finish time of two
activities determines the required finish time of the successor. When this
situation occurs, it is advantageous to split the successor activity into two
so the first part of the successor activity can start earlier but still finish
in accordance with the applicable finish-to-finish constraint.
Finally, the definition of activity windows can be
extremely useful. An activity window defines a permissible period in which a
particularly activity may be scheduled. To impose a window constraint, a
planner could specify an earliest possible start time for an activity (WES) or
a latest possible completion time (WLF). Latest possible starts (WLS) and
earliest possible finishes (WEF) might also be imposed. In the extreme, a
required start time might be insured by setting the earliest and latest window
start times equal (WES = WLS). These window constraints would be in addition to
the time constraints imposed by precedence relationships among the various
project activities. Window constraints are particularly useful in enforcing
milestone completion requirements on project activities. For example, a
milestone activity may be defined with no duration but a latest possible
completion time. Any activities preceding this milestone activity cannot be
scheduled for completion after the milestone date. Window constraints are
actually a special case of the other precedence constraints summarized above:
windows are constraints in which the precedecessor activity is the project
start. Thus, an earliest possible start time window (WES) is a start-to- start
lead.
One related issue is the selection of an
appropriate network representation. Generally, the activity-on-branch representation
will lead to a more compact diagram and is also consistent with other
engineering network representations of structures or circuits. For example, the
nine activities shown in Figure 2-4 result in an activity-on-branch network
with six nodes and nine branches. In contrast, the comparable activity- on-node
network shown in Figure 1-6 has eleven nodes (with the addition of a node for
project start and completion) and fifteen branches. The activity-on-node
diagram is more complicated and more difficult to draw, particularly since
branches must be drawn crossing one another. Despite this larger size, an
important practical reason to select activity-on-node diagrams is that numerous
types of precedence relationships are easier to represent in these diagrams.
For example, different symbols might be used on each of the branches in Figure
1-6 to represent direct precedence, start-to-start precedence, start-to-finish
precedence, etc. Alternatively, the beginning and end points of the precedence
links can indicate the type of lead or lag precedence relationship. Another
advantage of activity-on-node representations is that the introduction of dummy
links as in Figure 2-1 is not required. Either representation can be used for
the critical path scheduling computations described earlier. In the absence of
lead and lag precedence relationships, it is more common to select the compact
activity-on-branch diagram, although a unified model for this purpose is
described in this Chapter. Of course, one reason to pick activity-on-branch or
activity-on-node representations is that particular computer scheduling
programs available at a site are based on one representation or the other.
Since both representations are in common use, project managers should be
familiar with either network representation.
Many commercially available computer scheduling
programs include the necessary computational procedures to incorporate windows
and many of the various precedence relationships described above. Indeed, the
term "precedence diagramming" and the calculations associated with
these lags seems to have first appeared in the user's manual for a computer
scheduling program.
If the construction plan suggests that such
complicated lags are important, then these scheduling algorithms should be
adopted. In the next section, the various computations
associated
with critical path scheduling with several types of leads, lags and windows are
presented.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.