Construction Planning:
Estimating Resource Requirements for Work Activities
In addition to precedence
relationships and time durations, resource requirements are usually estimated
for each activity. Since the work activities defined for a project are
comprehensive, the total resources required for the project are the sum of the
resources required for the various activities. By making resource requirement
estimates for each activity, the requirements for particular resources during
the course of the project can be identified. Potential bottlenecks can thus be
identified, and schedule, resource allocation or technology changes made to
avoid problems.
Many formal scheduling procedures
can incorporate constraints imposed by the availability of particular
resources. For example, the unavailability of a specific piece of equipment or
crew may prohibit activities from being undertaken at a particular time.
Another type of resource is space. A planner typically will schedule only one
activity in the same location at the same time. While activities requiring the
same space may have no necessary technical precedence, simultaneous work might
not be possible. Computational procedures for these various scheduling problems
will be described in Chapter 2. In this section, we shall discuss the
estimation of required resources.
The initial problem in estimating
resource requirements is to decide the extent and number of resources that
might be defined. At a very aggregate level, resources categories might be
limited to the amount of labor (measured in man-hours or in dollars), the
amount of materials required for an activity, and the total cost of the
activity. At this aggregate level, the resource estimates may be useful for
purposes of project monitoring and cash flow planning. For example, actual
expenditures on an activity can be compared with the estimated required
resources to reveal any problems that are being encountered during the course
of a project. Monitoring procedures of this sort are described in Chapter 3.
However, this aggregate definition of resource use would not reveal bottlenecks
associated with particular types of equipment or workers.
More detailed definitions of
required resources would include the number and type of both workers and
equipment required by an activity as well as the amount and types of materials.
Standard resource requirements for particular activities can be recorded and
adjusted for the special conditions of particular projects. As a result, the
resources types required for particular activities may already be defined. Reliance
on historical or standard activity definitions of this type requires a standard
coding system for activities.
In making adjustments for the
resources required by a particular activity, most of the problems encountered
in forming duration estimations described in the previous section are also
present. In particular, resources such as labor requirements will vary in
proportion to the work productivity, Pij,
used to estimate activity durations in Equation (9.1).
From the planning perspective,
the important decisions in estimating resource requirements are to determine
the type of technology and equipment to employ and the number of crews to
allocate to each task. Clearly, assigning additional crews might result in
faster completion of a particular activity. However, additional crews might
result in congestion and coordination problems, so that work productivity might
decline. Further, completing a particular activity earlier might not result in
earlier completion of the entire project, as discussed in Chapter 10.
Example 1-5: Resource Requirements for Block
Foundations
In placing concrete block
foundation walls, a typical crew would consist of three bricklayers and two
bricklayer helpers. If sufficient space was available on the site, several
crews could work on the same job at the same time, thereby speeding up completion
of the activity in proportion to the number of crews. In more restricted sites,
multiple crews might interfere with one another. For special considerations
such as complicated scaffolding or large blocks (such as twelve inch block), a
bricklayer helper for each bricklayer might be required to insure smooth and
productive work. In general, standard crew composition depends upon the
specific construction task and the equipment or technology employed. These
standard crews are then adjusted in response to special characteristics of a
particular site.
Example 1-6: Pouring Concrete Slabs
For large concrete pours on horizontal slabs, it is important
to plan the activity so that the slab for a full block can be completed
continuously in a single day. Resources required for pouring the concrete
depend upon the technology used. For example, a standard crew for pumping
concrete to the slab might include a foreman, five laborers, one finisher, and
one equipment operator. Related equipment would be vibrators and the concrete
pump itself. For delivering concrete with a chute directly from the delivery
truck, the standard crew might consist of a foreman, four laborers and a
finisher. The number of crews would be chosen to insure that the desired amount
of concrete could be placed in a single day. In addition to the resources
involved in the actual placement, it would also be necessary to insure a
sufficient number of delivery trucks and availability of the concrete itself.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.