1. What is
the object of scheduling?
Scheduling means putting the plan on calendar basis. A project
network shows the sequence and
inters dependencies of activities, their time and their
earliest and latest completion time, but these needs to be scheduled to
determine commencement and termination dates of each activity. Using optimum
resources or working within resource constraints, it is a time table of work. A
basic distinction exists between resource oriented scheduling techniques. The
project is divided into number of operations.
2. List out
the advantages of scheduling.
1.. By
studying of any work and the many alternative methods of execution, we can
choose the best one.
2. It gives
a clear idea regarding the required men, materials, and equipments at different
stages of
work.
3. Resource
utilization is optimized.
4. Actual
progress of the work is monitored with the actual plan. If there is any delay,
proper remedial measures can be taken to avoid such delays.
3. What is
the purpose of work scheduling?
The bar - chart
type work schedule provides a simplified version of the work plan, which can
easily be understood by all concerned with planning, co -
ordination, execution, and control of the project.
(b) It
validates the time objectives:
A work schedule shows the planned sequence of activities, data
- wise
while putting the work
plan on a calendar basis; it takes into account reduced
efficiency of resources to adverse climatic conditions and other factors.
(c) It
evaluates the implications of scheduling constraints:
A work
schedule brings out the implications of constraints and enables preparation of
a plan of work within the frame work of these constraints.
4. What are
the steps involved in schedule chart?
(a) Select
the EST point of activity layout on the graph, and draw a line sloping equal to
its rate of execution i.e., 1 unit per day.
(b) Plot the
lowest rate slowing line and mark its intersection with the top to foundation
horizontal
line.
(c) Starting
from the point of intersection, move forward horizontally on the top line and
identify latest completion point of subsequent activity as indicated by the set
back.
5. What are
the factors affecting work scheduling?
(a) Time:
Most of the projects carry time constraints in the
form of imposed dates, these dates may include constraints on start and
completion of activities.
(b) Manpower:
Man power is one of the main in the successful execution of
projects. The idle labour time is paid
for and
the strikes and breakdown of work are kept in view by manpower.
(c)
Materials:
Construction materials are increasingly becoming
scarce and their procurement is a time consuming process. The schedule aids in
forecasting of materials and their timely supply determines the economics and
progress work.
6. What is
the purpose of numbering events?
i. It
simplifies the identification and description of a n activity in terms of event
numbers.
ii. The
activities are coded as i- j where i and j are the event numbers as
commencement and termination of an activity.
iii. It helps
in developing identification code for computer application.
iv. It systematizes the computations of critical
path for each activity as far as possible, the number of the proceeding event
it should be less than that of the succeeding event.
7. Define
the following terms:
1.
Critical path:
The longest path through the network is called
critical path and its length determines the minimum durations in which the
project can be completed.
2. PERT
(Program Evaluation and Review Technique):
PERT is vent oriented. It is parabolistic model
i.e., it takes into account uncertainties involved in the estimation time of a
job or an activity. It uses three estimates of the activity time, optimistic
time and pessimistic time and, most likely time.
3. Dummy
activity:
It is superimposed activity, which does not
represent any specific operation or process. It has zero duration and consumes
no resources, its purpose is
twofold. (a) To provide a logical link to maintain the
correct.
(b) To simplify the description of concurrent activities in
terms of event numbers. The dummy activity is drawn like any other activity,
but with dotted lines.
8. What is
the significance of critical path?
(a) It is the
longest path in the network; however it is possible for a network to have more
than one critical path. The sum of the durations of critical activities along
the critical path determines
the duration of the project.
(b). It is the
most sensitive path, any change in duration critical activities along the
critical path is bound to effect the duration of the entire project.
9. Define
the following terms.
1. EST
(Earliest Start Time):
This is the earliest time an activity can be
started, assuming that all the activities prior to it have taken place as early
as possible.
2. LST
(Latest Start Time) :
This is the latest time an activity can start
consistent, with the completion of the project in the stipulated time. The LST
of an activity is determined by subtracting the activity duration from the LFT
3. EFT
(Earliest Finish Time):
It is the earliest time by which an activity can
be completed assuming that all the activities prior to it begin at their EST.
4. LFT
(Latest Finish Time):
It is the latest time by which an activity must be
completed to ensure the completion of project within the stipulated time.
10. What
are the classifications of networks?
1. Skeleton
network
2. Master
network
3. Detail
network
4. Summary
network.
11.Define
the following terms: (a) Float:
The difference between the latest start time and earliest
start time of an activity is called as float.
Float is a measure of the amount of time by which the start of
an activity can be delayed consistent with the completion of the project on
time.
(b) Total
Float:
Total float of an activity is defined as the difference
between the maximum duration of time
available
for the completion and duration required to carry out that duration.
12.What is
mean by resource leveling and crashing? Resource leveling:
The aim is reduce the peak resource requirements
and smooth out period to period assignment within a constraint on the project
duration.
Crashing:
Higher amounts of direct activity cost would be
associated with smaller activity duration times, while longer duration time
would involve comparatively lower direct cost. Such deliberate reduction of
activity times by putting in extra effort is called Crashing.
13. Define
the following terms:
1. Normal
cost:
Normal
cost is the lowest possible direct cost required to complete an activity.
2. Normal
time:
Normal
time is the maximum time required to complete an activity at normal cost.
3. Crash
time:
Crash time is the minimum possible time in which
an activity can be completed using additional resources.
4. Crash
cost:
Crash
cost is the direct cost i.e., anticipated in completing an activity within the
crash time.
14. Define
activity cost slope.
Activity cost slope is the rate of increase in the cost of
activity per unit with a decrease in time.
The cost
slope indicates the additional cost incurred per unit of time saved in reducing
the duration of an activity.
Activity
Cost slope = crash cost - Normal
cost .
/ Normal time - Crash
time
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.