Home | | Construction Planning and Scheduling | Additional resource constraints

Chapter: Civil : Construction Planning And Scheduling

Additional resource constraints

Additional resource constraints
Civil - Construction Planning And Scheduling - Scheduling with Resource Constraints and Precedence - Additional resource constraints.

Additional resource constraints.

 

As another example, suppose that only one piece of equipment was available for the project. As seen in Figure 2-17, the original schedule would have to be significantly modified in this case. Application of the resource constrained scheduling heuristic proceeds as follows as applied to the original project schedule:

 

1.  On day 4, activities D and C are both scheduled to begin. Since activity D has a larger value of late start time, it should be re-scheduled.

 

2.      On day 12, activities D and E are available for starting. Again based on a later value of late start time (15 versus 13), activity

 

D is deferred.

 

3.      On day 21, activity E is completed. At this point, activity D is the only feasible activity and it is scheduled for starting.

 

4.  On day 28, the planner can start either activity G or activity H. Based on the later start time heuristic, activity G is chosen to start.

 

5.     On completion of activity G at day 30, activity H is scheduled to begin.

 

The resulting profile of resource use is shown in Figure 10-18. Note that activities F and I were not considered in applying the heuristic since these activities did not require the special equipment being considered. In the figure, activity I is scheduled after the completion of activity H due to the requirement of 4 workers for this activity. As a result, the project duration has increased to 41 days. During much of this time, all four workers are not assigned to an activity. At this point, a prudent planner would consider whether or not it would be cost effective to obtain an additional piece of equipment for the project.

 

Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Construction Planning And Scheduling : Additional resource constraints |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2024 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.