Sleepers for
Turnouts
A railroad turnout is a mechanical installation that enables
trains to be guided from one line of rail tracks to another. In this section we
discuss sleepers and sleeper designs for turnouts.
Prestressed
concrete sleepers for turnouts
Due to the acute shortage of wood, especially of long timbers
required for points and crossings, it was felt necessary to develop PRC
sleepers for use on turnouts in track-circuited areas. RDSO developed a PRC
sleeper design with a rectangular cross section in July 1986 for 1 in 12
left-hand turnouts with a 7730-mm curved switch for use with 52-kg rails. These
PRC sleepers for turnouts have been manufactured in the PRC sleeper factory at
Khalispur, and these sleepers are on trial on Northern Railways at present. The
salient features of these sleepers are the following.
(a) The
sleepers have a rectangular cross section.
(b) There are
74 sleepers comprising 2l sleepers in switch assembly, 3 in intermediate
sub-assembly and 18 in crossing sub-assembly.
(c) The
sleepers are of varying lengths and design. There are 16 different turnout
sleeper designs.
(d) These
sleepers require the use of a number of fittings different from the existing
standard fittings. The grooved rubber pads are of a standard 4.5 mm thickness,
but of varying size.
New
fan-type concrete sleeper for turnouts
The prestressed concrete sleepers discussed above are suitable
only for 1 in 12 turnouts. RDSO has developed a new fan-type sleeper that can
be used for 1 in 8.5 as well as 1 in 12 turnouts.
The new
design of concrete sleepers has the following characteristics.
(a) The cross
section of the sleeper in the new design is trapezoidal instead of rectangular
as in the earlier design.
(b) The
layout of the sleepers is fan shaped and the same design of sleepers can be
used for right-hand as well as left-hand turnouts by rotating them 10 o in a
horizontal plane.
(c) Apart
from approach sleepers, 54 concrete sleepers are used for 1 in 8.5 turnouts and
83 concrete sleepers are used for 1 in 12 turnouts.
(d) The
concrete used has a 28-day crushing strength of 600 kg/cm2.
(a) The
sleepers are laid perpendicular to the main line on the switch portion. In the
lead portion, sleepers are laid equally inclined to the straight and turnout
tracks. In the crossing portion, the sleepers are laid perpendicular to the
bisecting line of the crossing.
(f) The
sleepers under the switch portion have dowels for fixing slide chairs with the
help of screws. These sleepers are laid perpendicular to the main line and,
therefore, can be used for both left-hand and right-hand turnouts.
(g) The mark
'RE' is provided on the fan-shaped PRC turnout sleepers at one end. The
sleepers should be so laid that the end with the RE mark is always laid on the
right-hand side.
Laying of the concrete sleepers on
turnouts
The turnout locations where
concrete sleepers are to be laid should have a clean ballast cushion of 30 cm
thickness. Extra ballast should be available on the cess and the area should
have good drainage. Depending upon the availability of space and various other
site conditions, one of the following three methodologies or their combinations
can be adopted for laying concrete sleeper turnouts.
l Assembling
the turnout at the site and replacing it during the block period by means of
either cranes or rollers.
l Carrying
parts of the assembled turnout on dip lorries and replacing them during the
block period.
l Replacing
the existing turnout sleeper by sleeper except for the switch portion, which
can be assembled as one unit.
The assembling and laying should
normally be done using a crane of suitable capacity. After removing old turnout
sleepers, the ballast bed at the level of the bottom of the concrete sleepers
for turnouts should be evened out. Vibrating rollers should be employed to the
extent possible for compaction of ballast bed.
Turnouts with concrete sleepers
can be maintained in any one of the following ways:
(a) using
points and crossing tamper,
(b) using
off-track tampers with lifting jacks, or
(c) measured
shovel packing.
In the case of emergencies such
as derailments, when the sleepers may be damaged, temporary repairs should be
carried out by interlacing wooden sleepers for permitting traffic with
restricted speed. The damaged concrete sleepers are replaced by a fresh lot of
turnout concrete sleepers as a permanent measure as early as possible. The
wooden sleepers and any other damaged sleepers are replaced one by one with new
turnout sleepers.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.