Maintenance
of Concrete
sleepers
The
following points need attention in the maintenance of concrete sleepers.
i)
Concrete sleepers should normally be maintained
with heavy on-track tampers. For spot attention, MSP or off-track tampers may
be used. The size of chips for MSP should be 8 mm-30 mm as required
(b) Only 30
sleeper spaces are to be opened out at a time between two fully boxed track
stretches of 30 sleepers length each in case a LWR track exists.
(c) Concrete
sleepers should be compacted well and uniformly to give a good riding surface.
Centre binding of mono-block concrete sleepers should be avoided, for which the
central 800 mm of the sleeper should not be hard packed.
(d) Both ends
of the concrete sleepers should be periodically painted with anticorrosive
paint to prevent corrosion of the exposed ends of prestressing wires. In the
case of two-block sleepers, the tie bars should be examined every year, and if
any sign of corrosion is noticed, the affected portion should be painted with
an approved paint.
(e) Mechanical
equipment should be used for laying and maintaining concrete sleepers as far as
possible.
(f) Wherever
casual renewal of concrete sleepers is to be done, the normal precautions
followed for LWR tracks should be taken.
(g) The
elastic rail clip should be driven properly to ensure that the leg of the clip
is flush with the end face of the insert. Overdriving and underdriving should
be guarded against, as these cause eccentric loading on the insulations,
resulting in their displacement and in the variation of load.
(h) A
vigilant watch should be kept to ensure that no creep occurs in any portion of
the concrete sleeper track or there is no excessive movement near the switch
expansion joint (SEJ).
(i) It must
be ensured that the rubber pads are in their correct positions. Whenever it is
found that the rubber pads have developed a permanent set, these should be
replaced by new ones. Such examinations can be done at the time of destressing.
Toe load can also be lost due to ineffective pads.
(j) Nylon or
composite insulating liners used with Pandrol clips should be examined
periodically for signs of cracking and breakage. Adequate care should be
exercised when driving the clip at the time of installation to prevent damage.
(k) One of
the biggest problems regarding the maintenance of a concrete sleeper track is
that the elastic rail clips get seized with malleable cast iron (MCI) inserts
not only during regular maintenance, but also during destressing, other
incidental works, and derailments. The following remedial measures are
suggested.
(i) At the
base depot, all the elastic rail clips and MCI inserts should be thoroughly
cleaned. Grease should then be applied on the central leg of the elastic rail
clip (ERC) and the eye of the MCI insert. These should then be driven into
place at the time of assembly of the service pan.
ii)
During service all the elastic rail clips must be
taken out from the MCI inserts and cleaned with a wire brush and emery paper,
specially on the central leg. The eyes of the MCI inserts must also be cleaned
of any debris or rusted material. The central leg of the ERC should then be
covered with good quality grease. The eyes of the MCI inserts should be smeared
with the same grease before the treated ERCs are driven back. This has to be
repeated every one year in corrosion prone areas. A maintenance checklist for
concrete sleepers is given in Table 7.7.
Table 7.7 Maintenance checklist
for concrete sleepers
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.