Concrete
sleepers: Laying
Concrete sleepers are heavy, and as such manual handling of
concrete sleepers is not only difficult, but may generally damage the sleeper
as well. In exceptional cases, however, manual handling, including manual
laying of concrete sleepers, is resorted to after taking adequate precautions.
In the case of the mechanical relaying system,
normally two portal cranes are used on Indian Railways and relaying is done
using prefabricated panels. The existing rail panels are removed by gantry
cranes, the ballast is levelled up, and prefabricated panels are then laid with
the help of portal cranes. The following operations are involved.
(a) Preparation
work at the site of relaying
(b) Pre-assembly
of panels in base depots
(c) Actual
relaying operation
(d) Post-relaying
work
The full details of the manual relaying method as
well as of the mechanical relaying system are given in Chapter 21.