Network Representation
Each
activity of the project is represented by an arc pointing in the direction of
progress in the project. The nodes of the network establish the precedence
relation-ships among the different activities.
Three
rules are available for constructing the network.
Rule 1. Each
activity is represented
by one, and only one, arc.
Rule 2. Each activity must be
identified by two distinct end nodes.
Figure
6.39 shows how a dummy activity can be used to represent two concurrent
activities, A and B. By definition, a dummy activity,
which normally is depicted by a
dashed
are, consumes no time or resources. Inserting a dummy activity in one of the
four ways shown in Figure 6.39, we maintain the concurrence of A and B, and
provide unique end nodes for the two activities (to satisfy rule 2).
Rule 3. To maintain the correct precedence
relationships, the following questions must be answered as each activity is added to the network:
i.What
activities must immediately precede the current activity?
ii.What
activities must follow the current activity?
iii.What
activities must occur concurrently with the current activity?
The
answers to these questions may require the use of dummy activities to ensure
correct precedences among the activities. For example, consider the following
segment of a project:
a)
Activity C starts immediately after A and B have
been completed.
b)
Activity E
starts only after B has been
completed.
Part (a)
of Figure 6.40 shows the incorrect representation of the precedence
relation-ship because it requires both A and B to be completed before E can
start. In part (b), the use of a dummy activity rectifies the situation.
Example
6.5-1
A
publisher has a contract with an author to publish a textbook. The (simplified)
activities associated with the production of the textbook are given below. The
author is required to submit to the publisher a hard copy and a computer file
of the manuscript. Develop the associated net-work for the project.
Figure
6.41 provides the network describing the precedence relationships among the
different activities. Dummy activity (2,3) produces unique end nodes for
concurrent activities A and B. It is convenient to number the nodes
in ascending order in the direction of progress in the project.
PROBLEM SET 6.5A
1. Construct
the project network comprised of activities A
to L with the following prece-dence
relationships:
a)
A, B, and C, the first activities of the project,
can be executed concurrently.
b)
A and B precede D.
c)
B precedes E,
F, and H.
d)
F and C precede G.
e)
E and H
precede I and J.
f)
C, D, F, and J precede K.
g)
K precedes L.
h)
I, G, and L are the
terminal activities of the project.
2. Construct
the project network comprised of activities A to P that satisfies the following
precedence relationships:
a.
A, B, and C, the first activities of the project,
can be executed concurrently.
b.
D, E, and F follow A.
c.
I and G follow both Band D.
d.
H follows both C and G.
e.
K and L follow 1.
f.
J succeeds both E and H.
g.
M and N succeed F, but
cannot start until both E and H are completed.
h.
succeeds M
and I.
i.
P succeeds 1, L, and o.
j.
K, N, and P
are the terminal activities of the project.
*3. The
footings of a building can be completed in four consecutive sections. The
activities for each section include (1) digging, (2) placing steel, and (3)
pouring cqncrete. The digging of one section cannot start until that of the
preceding section has been completed. The same restriction applies to pouring
concrete. Develop the project network.
4. In
Problem 3, suppose that 10% of the plumbing work can be started simultaneously
with the digging of the first section but before any concrete is poured. After
each section of the footings is completed, an additional 5% of the plumbing can
be started provided that the preceding 5% portion is complete. The remaining
plumbing can be completed at the end of the project. Construct the project
network.
5. An
opinion survey involves designing and printing questionnaires, hiring and
training personnel, selecting participants, mailing questionnaires, and
analyzing the data. Construct the project network, stating all assumptions.
6. The
activities in the following table describe the construction of a new house.
Construct the associated project network.
7. A
company is in the process of preparing a budget for launching a new product.
The fol-lowing table provides the associated activities and their durations.
Construct the project network.
8. The
activities involved in a candlelight choir service are listed in the following
table. Construct the project network.
9. The
widening of a road section requires relocating ("reconductoring")
1700 feet of 13.8-kV overhead primary line. The following table summarizes the
activities of the project. Construct the associated project network.
10. The
following table gives the activities for buying a new car. Construct the
project network.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.