Future of Track Machines on Indian
Railways
Indian Railways has purchased
over 430 tie tamping machines during the last few years, which have been giving
satisfactory results. These machines have been found most suitable for wooden
and concrete sleepers and the condition of the sleepers maintained using these
tie tampers is definitely superior to those maintained by the conventional
method of beater packing. Indian Railways is systematically introducing long
welded rails and concrete sleepers on high-speed routes and the tie tamping
machine is ideally suited for the maintenance of such tracks. However, the
following points require special consideration for the successful
implementation of mechanical methods of maintenance on Indian Railways.
Blocks Adequate
time blocks of about 3 to 4 hours/day should be made available so as to make
mechanized maintenance effective and economical.
Ballast cushion A clean
ballast cushion of a depth of about 20 cm (8") should be available
below the sleeper bed of each track that is to be maintained mechanically.
Repair facilities Adequate
facilities for repair and overhauling should be made available at the
site and in the workshop.
Spare parts A good
stock of spares should be kept ready at hand to ensure that the machines
are always in good working order.
Training of staff The staff
employed for working the tie tamping machine should have thorough
knowledge of the principles and method involved in its working. A full-fledged
training school equipped with the necessary models and equipment should be made
available to train the staff hired for the mechanical maintenance of tracks.
Tier System of Track Maintenance
With the introduction of concrete
sleepers and on-track tamping machines on Indian Railways, three-tier system of
track maintenance is being adopted on all sections nominated for mechanized
maintenance. This system consists of the following three tiers of track
maintenance.
(a) On-track
machines units (OMU)
(b) Mobile
maintenance units (MMU)
(c) Sectional
gang
Tier 1: On-track machines unit
The work of systematic mechanized
maintenance of track is done with help of heavy on-track machines, which
include tie tamping machines for plain tracks as well as points and crossings,
shoulder ballast cleaning machines, ballast cleaning machines, ballast
regulating machines, and dynamic track stabilizers. These machines are used
when the following tasks are to be performed.
(a) Systematic
tamping of plain track as well as of points and crossings
(b) Intermediate
tamping of plain tracks as well as of points and crossings
(c) Shoulder
ballast cleaning, ballast profiling/redistribution, track stabilization,
periodical deep screening
Tier 2: Mobile maintenance units
Picking up of slacks and other
related works are done with the help of mobile maintenance units (MMU). The
Railways use two kinds of MMUs whose functions are as listed below.
MMU-1 (Rail-cum-road vehicle
based) One such unit is provided to each PWI in charge of a
40-50 km long double line or a 90-100 km long single line with a view to
carrying out the following work.
(a) Need-based
spot tamping
(b) Casual
renewal and repairs, except planned renewals; in situ rail welding
(c) Overhauling
of level crossings
(d) Replacement
of glued joints as well as rail cutting or drilling and chamfering
(e) Permanent
repair of fractures
(f) Creep or
gap adjustments involving the use of machines; destressing of LWR/ CWR
(g) Loading/unloading
of materials and other miscellaneous functions
MMU-II (Road vehicle based) One such
unit should be kept aside for each subdivision. It is used for the
reconditioning of turnouts and for the minor repairs of the various equipment
that are a part of the MMUs. A list of all the equipment included in the two
MMUs is given below.
Components of MMU-I Spot
tamping machines such as track tampers and lifting jacks, rail
cutting and drilling equipment, rail welding equipment, destressing equipment
for rail tension, etc., gas cutting equipment, material handling equipment,
safety and protection equipment, inspection gadgets and communication
equipment.
Components of MMU-II Reconditioning
equipment for points and crossings such as the welding generator,
arc welding equipment, hand-held rail grinder, equipment such as spanner and
gadgets for minor repairs.
Tier 3: Sectional gangs
Under the three-tier system of
track maintenance the section gangs are required to perform the following
functions.
(a) Patrolling
of the track, namely, the keyman's daily patrol, hot/cold weather patrolling,
monsoon patrolling, patrolling of vulnerable locations
(b) Dealing
with emergencies by carrying out temporary repairs as in the case of fractures
(c) Giving
need-based attention to bridges, turnouts, SEJs, and approaches to level
crossings
(d) Greasing
of ERCs, lubrication of joints, casual changing of rubber pads and other
fittings
(e) Minor
cess repairs, cleaning of drains, and boxing of ballast
(f) Paying
attention to loops
(g) Creep and
gap adjustment not involving the use of machines
(h) Cleaning
of crib ballast for effective cross drainage
(i) Pre- and
post-tamping attention
(j) Assistance
in the working of MMU and OMU as required
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.