UNLOADING
PROCEDURES
There are a number of
procedures that must be followed to properly unload a vessel. These procedures
are described below.
Grounding
After the vessel is moored and all safety
precautions are taken, the vessel must be grounded to the dock before cargo
hoses are connected. To ground a vessel, take the following steps:
§
Inspect the grounding system to
verify continuity and testing according to applicable standards.
§
Make sure the grounding switch is
open.
§
Make sure the grounding clamp on
the ship grounding clamp is attached to a bare metal surface on the hull of the
vessel. It may be necessary to sand a spot on the hull to make a good
connection.
§
Check the grounding system to see
that there are no loose connections.
§
Close the grounding switch.
Inspecting
Vessel
The master of the vessel and the shore petroleum
inspector must review the loading plan of the vessel for grades and amount of
products carried. Also, they must review the layout of the cargo and the order
in which products should be unloaded. Before unloading operations begin, the
shore petroleum inspector must check the manifest and DD Form 250-1 for serial numbers of
valve seals. The inspector must verify that each seal is intact on isolation
valves and sea suction valves. He must document reasons for missing or broken
seals. Ullages, temperatures, and water soundings must be taken on each
compartment by ship personnel and witnessed by shore personnel. These readings
are recorded on DA Form 3853-3. Great differences
in compartment gages after loading and before discharging must be checked
promptly. The vessel's master must explain these differences in a written
statement attached to the ullage report.
Sampling
and Testing Product
If the product aboard the vessel has been inspected
on procurement by the government, unloading operations may begin after a type C
test of an all-levels sample of product from each compartment shows no
contamination. Multiple tank composite samples must then be sent to the
laboratory for type B-1 tests. If the product aboard the vessel has not been
inspected on procurement by the government, the laboratory must run a type A
test on samples from the upper, middle, and lower portions of each tank or an
all-levels composite sample from each tank before discharge. If no testing
facilities are readily available, any product in question should be placed in
isolated storage until laboratory tests confirm quality.
Connecting
Cargo Hose
The steps for connecting the cargo hose to unload a
vessel are the same as those used to connect it to load a vessel. See page 4-18
for these steps.
Connecting
Loading Arms
The steps for connecting loading arms to unload a
vessel are the same as those used to connect them to load a vessel. See page
4-19 for these steps.
Heating
Cargoes
The cargo may need to
be heated before it is unloaded. See the information on heating cargoes given
on page 4-20.
Pumping
Product
There are certain
procedures that must be followed to unload product from vessel to shore. These procedures
are as follows:
§
Open the proper valves aboard the
vessel so that product will flow from the correct tank to the dock manifold.
§
Open the proper shore valves to
permit flow to the proper shore tank.
§
Start the pumps, and operate them
at a slow speed. Closely watch the pumping pressure shown on the pressure gage.
The gage is usually in the line near the dock manifold. If too much pressure
builds up quickly, it means a valve is closed in the line. In this case, shut
down the pumps at once. Do not start pumping again until the problem is
corrected.
§
Sometimes, shore pumps are used to
boost product flow. When this happens, adjust the discharge rate of the vessel
and the shore pumps after the pumps are started. This is done to prevent shore
location pump fuel starvation and to decrease discharge time.
§
Watch all hose and line connections
for leaks. If leaks appear, stop the pumps immediately, and fix the leaks
before starting again. A line walker should inspect the lines for leaks at
least once every hour.
§
Gage the shore tanks during the
unloading operation only as directed in the orders. The JP-5 and JP-8 shore
tanks should not be gaged during unloading operations.
§
Carefully watch for changes in the
tide and for slack or pull in the hose. Sudden movement of the vessel may cause
damage to the hose and loss of product.
§
In case of fire on the vessel or
dock or near the shore line or tank farm area, stop the transfer operations
immediately and close all the valves. If the tank farm is next to the port,
disconnect the cargo hose and move the vessel a safe distance from shore.
§
When an electrical storm is within
a 3-mile radius of the transfer operation, stop transfer operations and close
the valves on the vessel and dock. Coordinate on the weather before transfer
operations are started. Maintain coordination during transfer operations if an
electrical storm is probable. If there is no immediate hazard, the hose may be
left connected. If there is an immediate hazard, the hose should be
disconnected and drained and the main block valve on shore should be closed.
§
When all the product has been
pumped from one cargo tank, open the valves of the next tank carrying the same
product and close the valves of the empty tank. Be careful not to pump water
ashore. The pump should continue operating while tanks are being switched.
§
Watch the draft of the vessel
during the unloading operation to make sure the vessel maintains proper trim.
§
When the shore tank nears capacity,
open the valves leading to the next tank with the same product. Top off the
first tank at a slower rate, and close the valves when the first tank is full.
§
When the last of a series of vessel
cargo tanks carrying the same product is almost empty, reduce the flow of
product. When all product has been pumped from the last tank, stop all the
pumps and close all line valves.
Performing
Follow-Up Procedures
Certain follow-up
procedures must be performed after a vessel is loaded. These procedures are as
follows:
§
The petroleum inspector or a
representative checks to see that the tank compartments are empty. He then
fills out a dry-tank certification on a DD Form 250-1 or on the vessel's
ullage report, or on both. The amount of any product that cannot be pumped
ashore will be estimated. The estimate will be entered on the dry-tank
certification.
§
A representative of the US
government does the final shore tank gaging. Sampling is witnessed by an
officer or agent of the vessel or another authorized representative.
§
The vessel's master may decide not
to wait until after the product settles to gage the shore tanks. In this case,
the estimated amount received, based on gages taken after unloading and before
the end of the settling period, may be entered on DD Form 250-1. A preliminary check
should be made 30 minutes after receipt. Any two successive gages that agree
are used as the correct gage.
§
Fresh stocks of product should be
allowed to settle for about two hours after they are added to shore tanks.
After the product has settled, the final official gages are taken and the volume
is corrected according to DA Pamphlet 710-2-2. These readings
are used for accountability and are noted on DD Form 250-1.
§
A composite sample, which is a
mixture of upper, middle, and lower samples, is taken from each shore tank. The
sample is tested according to MIL-HDBK-200.
§
Ballast water is pumped into the
proper tanks if the vessel needs ballast to maintain trim during the voyage.
Tanks must be clean before ballast is received, and only clean water should be
pumped aboard.
§
When all the tanks are empty and
the ballast is loaded, all compartment hatches are closed and bolted down
securely. All ullage sounding holes should be securely covered.
§
All line valves should be closed.
The cargo hose must be disconnected, and any remaining product must be drained
from the hose. Spills are caught in drip pans placed beneath the hose
connection. The hose should not be allowed to drain into the water or on the
dock. If spills occur, they must be wiped up at once. The hose ends must be
covered with blind flanges and gaskets. The hose is stored in a shelter or hose
rack.
§
The cargo hose must be
disconnected, and the grounding switch must be opened. The bonding cable is
then disconnected from the ship
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.