DETAILED
SPECIFICATIONS OF EXCAVATIONS, FILLING
AND BACK
FILLING
Scope of
Work
The scope for work covered under this specifications
pertain to excavation of foundations, trenches, pits and over areas, in all
sorts of soil, soft and hard rock, correct to dimensions given in the drawing
including shoring, protections of existing underground utilities of any, such
as water lines, electric cables etc. dewatering and shoring if necessary,
stacking the useful materials as directed within the lead specified, refilling
around the foundation and into the plinth with selected useful excavated earth
and disposing off the surplus earth / materials within specified lead and
finishing the surface to proper levels, slopes and camber etc. all complete.
Site
Clearance:
Before the earth work is started the area coming
under cutting and filling shall be cleared of all obstruction, loose stones,
shrubs, rank vegetation, grass, bushes and rubbish removed up to a distance of
150 metres outside the periphery of the area under clearance. This work is
deemed to be included in the earthwork item rate and no separate payment will
be admissible.
Roots and
Vegetation clearance:
The roots of trees if any shall be removed to a minimum depth
of 60 cm below ground level or a minimum of 30 cm below formation level
whichever is lower and the hollows filled up with earth leveled and rammed.
This work is deemed to be included in the earthwork items and no separate
payment will be admissible for the work. Any material obtained from the site
will be the property of the Government of India and the useful materials as
decided by the Engineer-in-charge will be conveyed and properly stacked as
directed within the lead specified.
Setting
out and making profiles:
Masonry or concrete pillars will be erected at
suitable points in the area to serve as benchmarks for the execution of the
work. These benchmarks shall be connected with G.T.S. or any other permanent
benchmark approved by the Engineer-in-charge. Necessary profiles with pegs,
bamboos and strings or Burjis shall be made to show the correct formation levels
before the work is started. The contractor shall supply labour and materials
for setting out and making profiles and Burjis for the work at his own cost and
the same shall be maintained during the excavation work. The Department will
show grid co-ordinate or other reference points. It shall bethe responsibility
of the contractor to set out center lines correctly with reference to the
drawings and install substantial reference marks. Checking of such alignment by
the Department will not absolve the contractor from his responsibility to
execute the work strictly in accordance with the drawings.
Excavation:
The contractor shall notify the Engineer-in-charge
before starting excavation and before the ground is disturbed, to enable him to
take existing level for the purpose of measurements. The ground levels shall be
taken at 5 to 15 metres intervals in uniformly sloping ground and at closer
distance where local mounds, pits, or undulations are met with, as directed by
the Engineer-in-charge. The ground levels shall be recorded in field books and
plotted on plans, which shall be signed by the Contractor and the
Engineer-in-charge, before the earthwork is actually started. The labour
required for taking levels, shall be supplied by the Contractor at his own cost.
The Contractor shall perform excavation in all types of soils, murrum, soft and
hard rock, boulders etc. in foundation, over areas and in trenches to widths,
lines, levels, grades and curves as shown in the drawing or lesser widths,
lines, levels, grades and levels as directed by the Engineer-in-charge and per
items in the schedule of quantities. The item in the schedule of quantities
shall specify the excavation in trenches or over areas.
For this
purpose, the excavation for any depth in trenches for foundation not exceeding
1.5m in width or 10sqm. on plan shall be described as excavation in foundation
trenches. Excavation exceeding 1.5m in width as well as 10sqm. on plan
(excluding trenches for pipes, cables etc.) and exceeding 30cm in depth shall
be described as excavation over areas.
Excavation exceeding 1.5m in width as well as 10sqm. on plan
but not exceeding 30cm. in depth shall be described as surface Excavation.
Classification
of Earth work:
The earthwork shall be classified under the
following main categories and measured separately for each category. All types
of soil, murrum, boulders, Soft rock, Hard rock.
All types
of Soils, Murrum, Boulders:
This includes earth, murrum, top deposits of
agricultural soil, reclaimed soil, clay, sand or any combination thereof ad
soft and hard murrum, shingle etc. which is loose enough to be removed with
spadies, shovel and pick axes. Boulders not more than 0.03 cum. in volume found
during the course of excavation shall also fall under this classification.
Excavation
in Soft Rock:
This shall include all materials which are rock or
hard conglomerate, all decomposed weathered rock, highly fissured rock, old
masonry, boulders bigger than 0.03 cum, in volume but not bigger than 0.5 cum.
and other varieties of soft rock which can be removed only with pick axes, crow
bars, wedges and hammers with some difficulty. The mere fact that the
contractor resorts to blasting and / or wedging and chiseling of reasons of his
own, shall not mean the rock is classifiable as hard rock.
Excavation
in Hard Rock :
This includes all rock other than soft rock
mentioned in para above 1.5.1 (b) viz. soft rock, occurring in masses, boulders
having approximate volume more than 0.5 cum. plain or reinforced cement
concrete, which can best be removed by chiseling and wedging where blasting
cannot be permitted owing to any restriction at site.
Excavation
in Hard Rock by Chiseling and Wedging:
Where blasting is not permitted and if the
Engineer-in-charge so desires, the excavation shall be done by chiseling and
wedging or any other agreed method.
Note: All the excavated hard rock
obtained shall be stacked properly and neatly within the specified lead
by the contractor as directed by the Engineer-in-charge
Excavation:
The excavation under all classifications in areas
in trenches or in pits shall be carried out systematically. Cutting shall be
done from top to bottom and not under pining or under cutting will be allowed.
The bottom and sides of excavation shall be dressed to proper level,
slopes, steps, camber etc. by removing high spots and ramming
thoroughly as directed by the Engineerin-charge. All the excavation shall be
carried out strictly to the dimensions given in the drawing. The width shall
generally be of the width of mudmat concrete and depth as shown in drawing or
as directed by the Engineer-in-charge, according to availability of the desired
bearing capacity of soil below. Any excavation if taken below the specified
depths and levels, the contractor shall at his own cost fill up such over cut
to the specified level with cement concrete 1:4:8 in case of excavation in all
types of soils an with cement concrete 1:2:4 in case of excavation soft and
hard rock. After the excavation is completed, the contractor shall notify the
Engineer-in-charge to that effect and no further work shall be taken up until
the Engineer-in-charge has approved the depth and dimensions an also the nature
of foundation materials, levels and measurements shall also be recorded prior
to taking up any further work.
Shoring:
Unless separately provided for in the schedule of
quantities, the quoted rate for excavation shall include excavation of slopes
to prevent falling in soil by providing and / or fixing, maintaining and
removing of shorting, bracing etc. The contractor would be responsible for the
design of shoring for proper retaining of sides of trenches, pits etc. with due
consideration to the traffic, superimposed loads etc. shoring shall be of
sufficient strength to resist the pressure and ensure safety from slips and to
prevent damage to work and property and injury to persons. It shall be removed
as directed after items for which It is required are completed should the slips
occur, the slipped materials shall be removed and slope dressed to a modified
stable slope. Removal of the slipped earth will not be measured for payment.
Dewatering:
Unless specifically provided for as a separate item in the
schedule of quantities, rate shall also include bailing or pumping out all
water which may accumulate in the excavation during the progress of further
works such as mud mat concrete, R.C. footings, shuttering etc. either due to seepage,
springs, rain or any other cause and diverting surface flow by bunds or other
means. Care shall be taken to ensure that the water discharged sufficiently
away from the foundations keep it free from nuisance to other works in the
neighborhood.
Disposal
of Excavated Materials: Antiquities:
Any finds
of archeological interest such as relics of antiquity, coins, fossils or other
articles of value shall be delivered to the Engineer-in-charge and shall be the
property of the Government.
Useful
Materials:
Any material obtained from the excavation which in
the opinion of the Engineer-ncharge is useful, shall be stacked separately in
regular stacks as directed by the Engineer-incharge and shall be the property
of the Government. No material excavated from foundation trenches of whatever
kind they may be are to be placed even temporarily nearer than about 3m from
the outer edge of excavation. Discretion of the Engineer-in-charge in such
cases is final. All materials excavated will remain the property of the
Department. Rate for excavation includes sorting out of the useful materials
and stacking them separately as directed within the specific lead. Material
suitable and useful for backfilling or there use shall be stacked in convenient
place but not in such a way as to obstruct free movement of materials, workers
and vehicles or encroach on the area required for constructional purposes. It
shall be used to the extent required to completely backfill the structure to
original ground level or other elevation shown on the plan or as directed by
the Engineer-in-charge. Materials not useful in anyway shall be disposed off,
leveled and compacted as directed by the Engineer-in-charge within a specified lead.
The site shall be left clan of all debris and leveled on completion.
Backfilling
in sides of Foundations, Plinth, Under Floor etc:
The backfilling shall be done after the concrete
or masonry has fully set and shall be done in such a way as not to cause
under-thrust on any part of the structure. Where suitable excavated material is
to be used for backfilling, it shall be brought from the place where it
was temporarily deposited and shall be used in backfilling.
The scope of work for backfilling/ filling in foundation, plinth, under floors
etc. shall include filling for all the buildings covered under the contract.
Surplus earth available from one building, if required, shall be used for
backfilling filling for other buildings also within the specified lead
mentioned in the item. All timber shoring and form work left in the trenches,
pits, floors etc. shall be removed after
their necessity ceases and trash of any sort shall be cleared
out from the excavation. All the space between foundation masonry or concrete
and the sides of excavation shall be backfilled to the original surface with
approved materials in layers not exceeding 150mm, in thickness, watered and
well consolidated by means of rammers to at least 90% of the consolidation.
Areas inaccessible to mechanical equipment such as areas adjacent to walls and
columns etc. shall be tamped by hand rammer or by hand held power rammers to
the required density. The backfill shall be uniform in character and free from
large lumps, stones. shingle or boulder not larger than 75mm. in any direction,
salt, clods, organic or other foreign materials which might rot. The
backfilling in plinth and under floor shall be well consolidated by means of mechanical
or hand operated rammers as specified to achieve the required density. Test to
establish proper consolidation as required will be carried out by the
Department at rates specified. Two tests per 50 sqm. will be taken to ascertain
the proper consolidation. The cost of tests carried out will be recovered from
the contractor's bill.
Filling
in Plinth and Under Floors:
After the available suitable excavated materials
are exhausted as backfilling, the contractor shall notify the
Engineer-in-charge of the fact and levels taken jointly with Engineerin-
charge. The earth, murrum, sand, gravel etc. or such materials suitable for
filling proposed to be filled under floors and so mentioned in t he item of
schedule of quantities shall then be brought to site from approved locations
and sources.
Earth
Filling:
The earth, soft murrum etc. so brought shall be
filled up in layers of 15 cm depth, each layer being well watered and
consolidated by approved hand or mechanical tampers or other suitable means to
achieve the required density.
Gravel or
sand filling:
Gravel if required to be filled under floors,
shall be single washed gravel of approved quality and of size varying from 12mm
t0 20mm. it shall be uniformly blind with approved type of soil and / or sand
to obtain full compaction. Gravel shall be filled in specified thickness and
shall be well watered and rammed entirely to the satisfaction of the Engineer-
in-charge.If sand is required to be filled under floors, it shall be clean,
medium grained and free from impurities. The filled in sand shall be kept
flooded with water for 24hrs. to ensure maximum consolidation shall be done by
the contractor at his own cost. The surface shall
then be well dressed and got approved from Engineer-in-charge
before any other work is taken over the fill.
Lead and
Lift:
Lead: The lead for disposal /
deposition of excavated materials shall be as specified in the respective
item of work. For the purpose of measurements of lead, the area to be excavated
or filled or area on which excavated material is to be deposited/ disposed off
shall be divided in suitable blocks and for each of the block, the distance
between center lines shall be taken as 28 the leads which shall be measured by
the shortest straight line route on the plan and not the actual route adopted.
Lift: Lift shall be measured from
ground level. Excavation up to 1.5m depth below ground level and
depositing excavated material on the ground shall be included in the item of
earthwork for various kinds of soil. Extra lift shall be measured in unit of
1.5m or part thereof. Obvious lift shall only be measured that is lifts
inherent in the lead due to ground slope shall not be measured, except for lead
up to 250m. All excavation shall be measured in successive stages of 1.5m
stating the commencing level. This shall not apply to cases where no lift is
involved as in hill side cutting.
Mode of
Measurements:
All excavation in areas having depth more than
30cm. pits, trenches etc. shall be measured net. The dimensions for the purpose
of payment shall be reckoned on the horizontal area of the excavations for the
purpose of payment shall be reckoned on the horizontal area of the excavation
at the base for foundations of the walls, columns, footings, rafts or other
foundations, multiplied by the mean depth from the surface of ground determined
by levels. Excavation for side slopes will not be paid for. Excavation in areas
having depths less than 30 cms. shall be measured as surface excavation on
square meter basis, mentioning the average depth of excavation.
Reasonable working space beyond concrete dimension
required for waterproofing and shuttering where considered necessary in the
opinion of Engineer-in-charge will be allowed in execution and considered for
payment for underground water tank, sump septic tank etc.
Where direct measurements of rock excavation are not possible,
volume of rock can be calculated on the basis of length, breadth, and depth of
stacks made at site as mentioned in para 1.5.1 (c). The net volume shall be
worked out by reducing it by 40% taking the voids into consideration as 40%.
Similarly to arrive at net quantity to be paid in the case of soil reduction at
20% of corresponding stack / truck measurements shall be made. The rate for
excavation shall include carting and disposing and leveling the excavated
materials within the specified lead. The rate shall also be inclusive of cost
of all tools, plants, explosives, shoring, dewatering at various stages,
labour, materials etc. to complete all the operations specified.
The
backfilling and consolidation in sides of foundation and in plinth with
excavated material will not be paid for separately. The rate quoted for
excavation shall be deemed to have been included the cost of stacking of
excavated materials, conveying within the specified lead, picking of selected
stacked materials, conveying it to the place of final
backfill, compaction to the required proctor density etc.
Payment for filling and consolidation inside the trenches, sides of
foundations, plinth etc. with selected materials brought by the contractor
other than the excavated material, shall be paid for separately as per the
rates in schedule of quantities which includes cost of such materials/
excavation, royalty, its conveyance within the specified lead, watering,
consolidating, dressing etc. Actual quantity
of
consolidated filling shall be measured and paid in cubic meters up to two
places of decimal. The rate quoted in cum. for items of excavation is deemed to
include the necessary additional quantity of excavation involved beyond the
plan dimensions of the work which may be necessary to be carried out for
carrying out the work in an engineering made, decided upon by the contractor.
Therefore no extra payment will be made for any excavation done other than the
required quantity as per the plan dimension indicated in the drawings.
Measurements for excavation over areas shall be determined by levels or by
"Dead men" or both at the discretion of the Engineer-in-charge. If
however the Engineer-in-charge decided on measurement by levels, levels of site
shall be jointly taken and recorded by the Engineer- incharge or his representatives
and the contractor, before commencement of the work and after completion of the
work and the quantity of work done shall be computed based on these levels. The
volume of earth work shall be computed based on "Simpson's formula ' or
any other approved method at the discretion of the Engineer-in-charge.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.