Joints of different structural
connections:-
a. jointing
of column to footing
b. jointing
of column to beams on top of column.
c. jointing
of column to beam at an intermediate.
d. jointing of beams
f. Forming
of joints of arched structures
g. joining
of joints of post tensioned structures.
h. joining
of precast to monolithic reinforced concrete structures.
a. Joining column to footing:-
This joint is usually rigid but
also can be hinge. A rigid joint can be made by placing the column into a calyx
of the footing or by using a welded joint the figure shows the three variations
of the this method.
a) Can be used for smaller b) for average and
for large footings
The opening of the calyx is 6-10
cm greater in all directions than the c/s of the column. This is enable the
vibrator to be operated while concreting at the bottom of the calyx &
checked by leveling before concreting. A similar steel plate is also put on the
lower end of the column when positioning the column. These two steel plates
must be on each other. The dimensions of these steel plates are from 100 x 100
x 10 to 150 x 150 x 10mm an chored in to the concrete after the column is put
in placed properly plumbed tow advantages of the calyx joint should be
mentioned
1 The
placing plumbing and fixing of the column as well as the subsequent filling of
the calyx with concrete is far simpler and requires less time then in the case
of a welded joint.
2 The
method is least sensitive to inaccuracies occurring during the construction.
The disadvantages of the calyx Joint is more suitable for
small columns. In the case of large columns requiring a calyx depth of which is
greater than 1.0m.
One members of joining a merge like joint consists
either of placing to beams on to as small cantilever protracting trans the
column or of putting it on the bottom of an adequately shaped opening deft out
of the column shaft. The beam rests temporarily on a tongue like extensist on a
steel plate placed in this opening on the supporting surface the tongue is also
furnished with a steel plate anchored in to the concrete. The other parts of
the tongue are supported after the placing has been finished with concrete cast
through an opening left for this purpose.
d.
Lengthing of columns:-
Columns are usually lengthened at
floor levels. An intermediate lengthening should be avoided it possible.
The lengthening of columns can be
executed similarly to the joining with fooling, accordingly reinforcement are
joined by overlapping looped steel bars a welding. Thereafter the stirrups have
to be placed & finally the joint must be concreted.
e) Joining of Beams:-
The functions of beams can be
affected either by overlapping the protracting steel bars or by welding them
together.
Figure shows the tinge like joint
of purlins. In this method the whole shear must be borm by both cantilever
(i.e) by two separate structures therefore it is expedient to form this joint atleast
for large girders.
The method illustrated in the fig
presents a dry joint of beams which is called a bolted form. The advantages of
this joint is immediate bearing capacity.
f) Forming of functions of arched structures:-
Precast arches are usually
produced and assembled in the form of three hinged structures. When the
constant load has already been applied the centre joint is frequently
eliminated. The omission of the centre joint increases the rigidity of the
structure. Naturally arched structures can also be precast in a piece i.e in
the form of two hinged ones.
Hinges of arched structures can be made by using either steel
shors are more expensive, but the centre transmission of forces is enhanced by
their use.
Figure shows the centre hinge of
a three hinged arch with a span of 12.5 m for this kind of each the joint can
also be formed from the concrete itself. The latter method require exactly
executed and adequately reinforced concave & convex surfaces with hear
against one another.
The
joining of a smaller hinged structure is show in below mentioned.
The arrangements the centre
junction of the end hige of an arched structure. This method was used in the
construction of the ball for the middle rolling train in D.O.Sayar. The
structure was precast & assembled in the form of a three-hinged arched
transformed later in to a two -hinged one.
g. Design of joints for post tensioned
structures:-
Post tensioned structures can
generally be joined for more simply then the usual reinforced concrete
structures, By using post tensioning it can be ensured that in the entire
structure. The joints included only compressive can develop consequently the
problem of joining can be solved in a very easy manner namely by placing plane
surfaces side by side and then filling the gaps with cement mortar.
precast member. Thus in post
tensioned structures the forming of joints does not cause difficults.
Sketches solutions of principles
relating to the joining of post tensioned structure are to be illustrated in
the fig. All these joints are of course rigid and moment bearing. It is not
permissible for the mortar which is to be poured into the gaps to follow in to
the ducts of the stressing lables to arid this cable ducts are jointed by
placing a shore piece of tube or rubber ring into the duct itself.
A regid point of their kind
established between a columned two girders supported by the former after the
casting of the gaps & hardening of the mortar, the short inserted cables
are stressed and so rigid joint is established.
h) Joining of precast to monolithic reinforced
concrete structures:-
If frequently occurs that a
monolithic beam has to be joined to a precast column in this by placing the protruding
from the column or into an opening formed in the column's shaft.
When making the joint, first of
all a 2.5 cm deep cavity is chielled out of the side of the precast column. The
bottom of this cavity should be roughened so as to attain a better bank between
the concrete of the monolithic beam and the precast column.
1.Explain
about Roofing members in etail.
Roofing
members are classified as,
i.Reinforced
planks.
ii.Light
weight concrete members.
iii.Small
reinforced roofing
members.
iv.purlins
v.Large reinforced
roofing
members.
Reinforced planks:
Reinforced planks made of hollow tiles.The
reinforced planks with longitudinal circular holes.Thickness of these tiles is
60mm,80mm & 100mm & the width is 200mm & length is vary from 360mm
to 400mm. On the upper side one longitudinal groove is provided.
Reinforcement
is placed into these grooves which are subsequently filled with cement
mortar.In this way ,roofs of length 2 to 3m & thickness of 60 to 100mm
& width 200mm can be constructed.
The end tiles resting on the support are provided
with 3.11mm dia stirrups protruding from the tile.There are kept together over
mortar of 40mm thickness & in further concreting of joint.the joint is
completed.
Light weight concrete roofing members:
Light weight concrete roofing members play a role
in addition to space bordering & load bearing in heat insulation.The
thickness varies from 7.5 to 25cm for reinforcement of Light weight concrete
roofing members.weiding nets is used.steel reinforcement is given additional
coating to prevent any corrosion care is taken to give good bonding of
reinforcement with concrete.
The unit weight of these members is 750kg/m3 &
width of 50cm.Its varies from 1.75mm to 6m.precast members can be made either
in usual way using light weight materials.sand as aggregate
& combination of high strength concrete.The top &
bottom layer of about 2 to 3cm thickness iss provided with high strength
concrete.Its consists of prestressed 2.5mm ddia embedded in these layers.The
middle portion is made with light weight concrete.
Small reinforced concrete roofing
members:
The Small reinforced
concrete roofing members
is essentially precast
simply
supported
ribbed concrete slab width varying from 450 to 120cm & length varying from
2 to 4m.
Purlin s:
Purlins are precast concrete beams supported by
the main girders serving the purpose of bearing for the roof covering.The cross
section of purlins iss generally rectangular but it can also have
trapezoidal,T,L and I shape.
Precast purlins can be simply supported or
cantilever beams & for the bearing of loads beyond these weight simply
supported purlins can be transformed into continuous beams.It is very simple
& easy to place.For cantilever purlins placing of hinges should be
determined in a manner to develop positive & negative moments equal to each
other.This can be arrived by placing the hinges @
0.1451
from the support where I is the spacing between the
supports.
Large reinforced concrete roofing members:
Large reinforced concrete rest on the main
girders.These are generally used for large hall structures & these are most
advanced type of precast structures.Members are manufactured corresponding to
spacing of the frame length of about 6 to 10m & width of 1.3 to 1.8m. As
they are most supported on main girder purlins are not required.
Four
kinds of members exist:
1.Normal
members.
2.Intermediate
members.
3.Members with cornice.
4.Members
with gutter & eves border.
2.Write a
detailed note on shear walls.
The types
are classified as
1.Rectangular
type or Bar bell type.
2.Coupled shear wall.
3.Framed shear type.
4.Core type shear wall.
When walls are to carry only compressive force,they can be
designed as plain concrete,when walls are subjected to tensile forces(due to
wind force)due to eccentric loading& earthquake load the walls are RC
walls,shear walls are previously provided to resist the wind forces only.Hence
became popylar & to prvide shear walls to resist EQ forces.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.