Home | | Estimation and Quantity Surveying | Important Question And Answer: Civil - Estimation and Quantity Surveying - Estimate of Buildings

Chapter: Civil : Estimation and Quantity Surveying : Estimate of Buildings

Important Question And Answer: Civil - Estimation and Quantity Surveying - Estimate of Buildings

Civil - Estimation and Quantity Surveying - Estimate of Buildings

 

ESTIMATE OF BUILDINGS

 

1..What are methods to be adopted for volume calculating?

 

        From cross-section

 

         From spot level

 

         From contours

 

2.Define analysis of rates.

 

Determination of rates of works from the qualities and cost of materials and labours required is termed as analysis of rates

 

3.Define a tender.

Tender is an offer given in writing to execute specified articles or materials at a certain

 

rate, within a fixed time, under certain conditions of agreement between the contractor and the party, which may be a government department or an individual.

4.Define 'contract'

 

Contract is merely an agreement being enforceable by law between two persons or

parties.

 

5.What are the types of culvert?

1.     Arch culvert

 

2.     Slab culvert

3.     Pipe culvert

4.     Box culvert

 

6.what are the methods of estimate?

1.Detailed estimate

 

2. Abstract estimate

 

7. What are the types of estimate?

1 Preliminary Estimate or Rough cost estimate

2. Plinth area estimate

3. Cube Rate Estimate or Cubical Content Estimate

 

4. Approximate Quantity Method Estimate

 

5. Detailed Estimate or Item Rate Estimate 6.Revised Estimate

 

7. Supplementary Estimate And Revised Estimate. 8.Annual Repair or Maintenances Estimate

9. Supplementary Estimate

 

8. Briefly explain about preliminary Estimate.

 

The estimate which prepared using any rough method to get the approximate cost construction anticipated in a project is called an approximate or rough estimate. Since this estimate is normally prepared in the preliminary estimate.

 

9.Estimate the quantities of brickwork and plastering required in a wall 4m long, 3m high and 30 cm thick. Calculate also the cost if the rate of brickwork is Rs.32.00 per cu.m and of plastering is Rs. 8.50 per sq.m

 

Quantities of brickwork  = LxBxH

 

= 4m x 3m x 0.30m

 

 

 

= 3.6 cu.m Quantity of plastering (two faces) = 2 x 4m x 3m

 

= 24sq.m Cost of brickwork =3.6 x 320.00

 

= Rs.1152.00 Cost of plastering = 24x 8.50

 

= Rs.204.00

 

Total cost =1152.00 + 204.00 = Rs.1356.00

10. Define detailed estimate

 

The estimate, which provides the itemwise quantities of works, item wise unit rates and itemwise expenditure anticipated in thre project/construction, is called a detailed estimate

 

11. Define Abstract estimate

 

This is the third and final stage in a detailed estimate. The quantities and rates of each item of work, arrived in the first two stages, are now entered in an abstract form. The total cost of each item of work is now calculated by multiplying the quantities and respective rates.

 

12. Define quantity surveyor

 

A qualified or experienced person who does the above mentioned works (taking off, squaring, abstracting and billing) is called a quality surveyor

 

13.            Write the duties of quantity surveyor.

         Preparing bill of quantities (Taking off, squaring, Abstracting and billing)

 

         Preparing bills for part payments at intervals during the execution of work.

 

         Preparing bill of adjustment in the case of variations ordered during the execution of work

 

         Giving legal advice in case of court proceedings

 

14.            Write the essential qualities of a good surveyor.

         The quality surveyor must be well versed with the drawings of work.

 

         He should be able to read the drawing correctly and bill the quantities accurately

 

         He  should  have  a  through  knowledge  of  the  construction  procedure  to  be

 

adopted, the various items of works involved in the execution: and the different materials to be used in the work.

 

         He should be able to prepare schedule to be priced by tenderor.

 

15.          What are the main components of culvert?

 

1.Abutments 2.Wing walls 3.Arch

 

 

Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Estimation and Quantity Surveying : Estimate of Buildings : Important Question And Answer: Civil - Estimation and Quantity Surveying - Estimate of Buildings |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.