Detailed Estimate
The preparation of
detailed estimate consists of working out quantities of various items of work
and then determines the cost of each item. This is prepared in two stages. I)
DETAILS OF MEASUREMENTS AND CALCULATION OF QUANTITIES
The complete work is divided into various items of work such as
earth work concreting, brick work, R.C.C. Plastering etc., The details of
measurements are taken from drawings and entered in respective columns of
prescribed preformed. The quantities are calculated by multiplying the values
that are in numbers column to Depth column as shown below:
Details of measurements form
ii) Abstract of Estimated Cost
:
The cost of each
item of work is worked out from the quantities that already computed in the
details measurement form at workable rate. But the total cost is worked out in
the prescribed form is known as abstract of estimated form. 4%of estimated Cost
is allowed for Petty Supervision, contingencies and Unforeseen items.
Types of Estimates
ABSTRACT OF ESTIMATE FORM
The detailed estimate should accompanied with
I) Report
ii) Specification
iii)Drawings (plans, elevation, sections)
iv)Design charts and calculations
Standard schedule of rates.