Methods Of Taking Out Quantities

The quantities like earth work, foundation concrete, brickwork in plinthand super structure etc., can be workout by any of following two methods: a) Long wall - short wall method b) Centre line method. c) Partly centre line and short wall method.


Methods Of Taking Out Quantities


 

The quantities like earth work, foundation concrete, brickwork in plinthand super structure etc., can be workout by any of following two methods: 

a) Long wall - short wall method 

b) Centre line method.

 

c) Partly centre line and short wall method.

 

LONG WALL-SHORT WALL METHOD

 

In this method, the wall along the length of room is considered to be longwall while the wall perpendicular to long wall is said to be short wall. To get thelength of long wall or short wall, calculate first the centre line lengths of individual walls. Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its centre line length. Thus the length of short wall

 

Measured into in and may be found by deducting half breadth from its centre linelength at each end. The length of long wall usually decreases from earth work tobrick work in super structure while the short wall increases. These lengths aremultiplied by breadth and depth to getquantities.

 

CENTRE LINE METHOD

 

This method is suitable for walls of similar cross sections. Here the totalcentre line length is multiplied by breadth and depth of respective item to get thetotal quantity at a time. When cross walls or partitions or verandah walls joinwith main all, the centre line length gets

 

reduced by half of breadth for eachjunction. Such junction or joints are studied carefully while calculating total centreline length. The estimates prepared by this method are most accurate and quick.

 

PARTLY CENTRE LINE AND PARTLY CROSS WALL METHOD

 

This method is adopted when external (i.e., around the building) wall isof one thickness and the internal walls having different thicknesses. In such cases,centre line method is applied to external walls and long wall-short wall method isused to internal walls. This method suits for different thicknesses walls and differentlevel of foundations. Because of this reason, all Engineering departments arepracticing this method.

 

Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Estimation and Quantity Surveying : Estimate of Buildings : Methods Of Taking Out Quantities |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.