Construction of New Railway Lines
The main work involved in the construction of a new line is
the following.
(a) Land
acquisition
(b) Earthwork
and bridges
(c) Station
building, staff quarters, and other allied facilities, including platforms and
sheds
(d) Plate
laying, including ballasting of track
(e) Opening
of section for traffic
1 Land Acquisition
The work of land acquisition
should start well in advance so that all legal and financial formalities are
completed on time and possession of the land can be taken for starting
construction work. Land acquisition is done with the help of the member state government
as per the procedure laid down in the land acquisition act. Normally Sections 4
and 6 of the Land Acquisition Act are applied for acquisition of land in India.
Land is generally acquired after giving a notice and paying compensation to the
previous occupants. In the case of an emergency, land can also be acquired
urgently by operating the Special Sections 9 and 17 of the Land Acquisition Act
in India.
The land to be acquired should be
adequate for the formation, berm, and borrow pits. It should also have adequate
provision for future expansion. Even when a single line is to be constructed,
the land available should be sufficient for the construct of a double line for
future expansion. Normally a strip of 25 to 35 m of land is acquired for the construction
of a railway line. For station yards, an extra width of land is acquired. For
small stations, the width normally adopted is 150 × 1000 m.
The
minimum land to be arranged should conform to the following.
Width of formation: The land
should be adequate to accommodate the width of formation.
(ii) Side
slope: The side slope depends on the nature of the soil and is
normally taken as 2:1 (horizontal:vertical).
(iii) Width of
berms: The usual width of the berm is kept at 3 m.
(iv) Borrow
pits: If the land is not very costly, adequate land should be made
available for borrow pits also. Borrow pits may be on one side of the track
for low banks and on both sides for medium and high banks. When the land is
costly, borrow pits need not be provided for and earth can be borrowed from
adjoining areas. Extra land is, however, required for station yards, level
crossings, and bridge approaches.
2 Earthwork for Formation
The formation may be in an
embankment or a cutting depending upon the rail level and general contour of
the area. A formation in an embankment is normally preferred from the point of
view of good drainage. The height of the embankment also depends on the high
flood level of the area and a reasonable free board is provided above this
level. The standard width of formation is given in Table 4.1.
Table 4.1 Standard width of
formation
Some points worth noting with
regard to the specifications for earthwork are as follows.
(a) Earthwork
is normally done in 30-cm-deep layers so that the soil is well compacted.
(b) Mechanical
compaction is normally done after each layer with the help of a 'sheep foot
roller' to obtain 90% of the maximum dry density at optimum moisture content.
(c) A
shrinkage allowance of 5% is made from the final cross section for
consolidation in the case of mechanical compaction. For other types of
compaction the shrinkage allowance is 10%.
(d) When the
soil is not good, a 30-cm-thick blanket is provided at the top of the
embankment.
(e) In areas
where there are both cuttings and embankments, the earth from the cuttings
should be used for the embankments up to an economical lead. The economical
lead of moving earth in the longitudinal direction is determined by the mass-haul
curve .
For the early execution of
earthwork, the section is normally divided into different convenient zones,
each zone having earthwork requirement costing approximately Rs 1.5 to 3
million. Tenders are invited for each zone separately so that work can progress
simultaneously in all zones.
3 Bridges
Bridges should be designed for
the heaviest locomotive likely to pass that section. Depending upon the
topography of the country and the type of stream to be crossed, hume pipe
culverts, reinforced cement (RCC) slab bridges, plate girders or prestressed
concrete (PRC) girder bridges or steel bridges, are designed. Bridges, being
important structures, are normally made for double-line tracks, even in
single-line sections, with a view to plan for future expansion.
For the construction of important
bridges, separate tenders are called, with design and construction details
included in the tender documents. Minor bridges and culverts are normally
included in the earthwork zones mentioned above.
4 Service Buildings and Staff Quarters
Service buildings include the
station master's office, telegraph office, etc., which are basically required
for providing services for running the trains. Apart from this, staff quarters
and other passenger amenity works such as platforms, foot over bridges, waiting
halls, and retiring rooms are also provided at stations. Many other ancillary
facilities such as water supply, drainage, telephone lines, and electricity are
also made available.
All these constructions are
simultaneously taken up by civil engineers, electrical engineers, and signal
engineers so that they can progress together.
5 Plate Laying or Track Linking
Once the formation is ready,
plate laying or track linking is required. It consists of laying rails,
sleepers, and fastenings. The following methodology is adopted for plate laying.
Tram Line Method
In this method, a temporary line
known as the 'tram line' is laid by the side of the proposed track for taking
track materials to the site. This method is useful in flat terrain, where
laying the tram line on natural ground may be comparatively easier. This method
is, however, seldom used in practice.
A modification of the above
method is the side method. This method is used where track and bridge
material is carried to the site on trucks on a service road parallel to the
track. The material is then unloaded near the work site. This method is used
only in cases where comparatively flat gradients are available.
American Method
In the American method, rails and
sleepers are first assembled in the base depot and pre-assembled track panels
are then taken to the site along with the necessary cranes, etc. The track panels
are unloaded at the work site either manually or with the help of cranes and
are then laid in the final position. This procedure is used in many developed
countries, particularly those where concrete sleepers are laid, since these
sleepers are quite heavy and it is not easy to handle them manually.
Telescopic Method
This method is widely used on
Indian Railways. In this method, the rails, sleepers, and other fittings are
taken to the base depot and unloaded. The track material is then taken to the
rail head and the track is linked and packed. The rail head is then advanced up
to the extent of laid track. The track material is then taken up to the
advanced rail head with the help of a dip lorry and the track is again linked
and packed. In this way, the rail head goes on advancing till the full track is
linked. The main operations involved are as follows.
Unloading of materials The track
material is taken to the base depot and unloaded with the help of
material gangs. The first base depot is the junction of the existing line and
the new line to be constructed. All track material is taken from the base depot
with the help of a dip lorry (a special type of trolley) to the rail head. The
rail head goes on advancing till the track is sufficiently linked. After that,
a subsidiary depot is established at a distance of about 5 km where the track
material is taken with the help of a material train. Alternatively, the track
material is moved from the base depot with the help of dip lorry only up to a
distance of about 2 km and by material train beyond this distance. In the base
depot, advance arrangements such as adzing and boring of the sleeper and
arrangement of matching materials are made so that the track is linked as soon
as possible to the site.
Track linking Once the
track material is unloaded, the track is linked with the help of linking
gangs. The following procedure is normally adopted.
1. A string
is first stretched along the centre line of the alignment and sleepers are laid
with their centres on the string. The sleepers are laid roughly at the desired
spacing, keeping the total number of sleepers per rail intact.
2. The rails
are carried by rail tongs and kept on the cess of the bank almost in the final
position. As carrying rails is a very strenuous job (each rail weighs above 600
kg and about 12-15 gangmen are required to carry one rail), a special type of
rail carrier known as the Anderson rail carrier can be used for carrying
rails with lesser strain.
3. The
sleepers are spread out on the formation. The rails have markings where the
final position of the sleepers should come.
4. Small
fittings such as fish plates and bolts are placed near the joints, other
fittings required for each sleeper are placed near the end of the sleeper.
5. The rails
are then placed on the sleeper and fixed with the help of fittings depending
upon the type of sleeper. For example, in the case of wooden sleepers, rail
screws are used for fixing the rails to the wooden sleepers. In the case of
steel sleepers, rails are fixed with the help of a key. Bearing plates are also
provided wherever required, as per the prescribed track standards.
6. The rails
are joined to each other keeping a proper gap. Now-a-days, normally three rail
panels are initially used for laying the track. In the case of single-rail
panels as well as three-rail panels, adequate expansion gaps should be left.
The recommended expansion gaps are provided with the help of steel liners or
shims of correct thickness (1-4 mm), which are fixed between the two rail ends.
Track packing The track
is then thoroughly packed with the help of beaters by 'packing-in-gangs'.
The following aspects should be checked.
(a) The track
should have a proper gradient.
(b) The track
should have proper curvature, if it is on a curve
(c) The cross
levels should be even. If superelevation is to be provided, the outer rail
should be raised so as to have the recommended superelevation.
(d) The track
should be thoroughly packed and no spaces should be left.
Ballasting of track The
ballast is normally spread on the railway lines after the embankment has
settled well and at least two monsoons have passed over it. Ballasting is
generally done with the help of ballast trains, which have special hoppers
through which the ballast can be automatically unloaded onto the track.
Alternatively, the ballast is carried on the cess and then laid on the track
manually. Using either method, the ballast is thoroughly packed and inserted
under the track.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.