Centering and shuttering
Shuttering is the temporary ancillary construction used as a mould for the structures In which the concrete is placed and allowed to hardened


Centering and shuttering

 

Shuttering is the temporary ancillary construction used as a mould for the structures In which the concrete is placed and allowed to hardened

 

These are classified as steel wooden plywood combined woods steel, reinforced concrete and plain concrete

 

Requirements of shuttering

The material should be cheap and should be suitable for re use several times

 

 

It should be practically water proof so that it should not observe water from concrete

 

It should be strong enough to with stand all loads coming on it

 

It should be stiff enough so that deflection is minimum

 

The surface of the formwork should smooth and it should afford easy stripping


 

Loads on form work

Live load due to labour etc

Dead weight of wet concrete

Hydrostatic pressure of the fluid concrete

Impact due t pouring concrete

 

Shuttering for column

Components

 

Sheeting or column shutter all around the column Yokes

 

Wedges bolt

 Shuttering for beam and slab floor

 

The slab is continous over the beam

 

The slab is supported on 2.5 cm thick sheeting laid parallel to the main beam

The boarding may be 4 to 5 cm thick for walls up to 3to 4m high

 

The boards are fixed to 5cmX10cm posts known as struts are soldiers

 


Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Construction Techniques, Equipment And Practices : Construction Practices : Centering and shuttering |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2024 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.