Equalent design loads for considering abnormal
effects like earthquake and cyclones
hoisting & placing differ
from those arising in their final position. Owing to this additional
reinforcement would be required which after the placing is finished becomes
unnecessary. The additional stresses as well as the reinforcement required to
resist them should be eliminated. The methods will differ from each individual
problem.
The most simple solution for the
elimination of erection stresses & surplus reinforcement connected with the
latter consists in the firm attachment of a steel beam to the member. The
figure shows the hoisting of a framewhere ends of the steel beam are wedged to
the stanchion while its middle is it down. In this way the developing BM due to
the dead load is bome partly by the steel beam as marked in the figure &
the remaining part can be bome by the stanchion itself without any additional
reinforcement.
After the beam has been
hoisted by 45', the temporary reinforcing steel beam
becomes
unnecessary & can be removed.
The same solution applied during
hoisting a multi storyed frame. For large structures the above method, owing to
great length & strong forces is no longer satisfactory & so here heavy
latticed steel structures would be necessary. Erection stresses developing
during hoisting in column & girders of high halls may be eliminated most
suitably by post tensioning with cables.
The stressing cables applied on
bothsides of the column are tensioned by gas threated jacks assembled to one
end of the column by a tensioned of 25+25=50 MP
The tensioning force is
controlled by measuring the reaction force developing above the hoisting pin
using a manometer.
During hoisting the moment
developing from post tensioning counter balances the moment arising from dead
load. In the column not only a BM arises but also a centric compression which
in the present case also exerts a beneficial effect. When the column has been
hoisted the equipment used for post tensioning has to be dismantled before
placing begins.
The same result might be achieved
by a temporary post tensioning of a shorter section of the column. This method
was used for post tensioning the column of power station at berente. Here the
post tensioning extended only over the section affected by a positive moment
during hoisting balancing the tensional force developing here.
The required tensioning force is
provided by a hydraulic jack. Naturally the magnitude of this force must be
measured.
Another
solution for elimination of erection stresses in this case the stanchion of a
frame to be transported are braced each other. During transportation. So
lessening the moments arising at points which are supported by scattolds set up
on the conveying trucks. The frames were precast in the upright position. To
save the extra trucks for the conveying trucks, the latter were moved on the
final sail tracks of the hall. This arrangement leads to the development of
great bracing reduces these moments considerably.
Manufacture, transport & erection of wall
panels:-
The manufacture of wall panels
depends primarily upon the c/s design of upon the desired surface treatment.
Hence it is perhaps the best procedure first to investigate the possibilities
before deciding the manufacturing procedure.
These possibilities can be
summarized as follows, according to the method of execution.
a) Surface
which is formed by the pattern or texture of the mould
b) Surface
finish produced by Mechanical treatment
c) Chemical
treatment of the surface
d) Paints
& Coatings.
a) Surface formed by Moulds:-
This method of producing the
desired surface pattern or texture used when the outer face of the wall panel
is downward in the mould. Initial case it will in general not be possible
directly to produce a smooth interface, as it is not formed by moulding, but it
merely given a float finish a higher degree of smouthness it will be necessary
to apply an additional finish operation.
The following methods are best
suited for producing a close-texture concrete surface free from pores or blow
wholes.
a) Resin-coated
mould surface
b) Plastic
-lised mould
c) Moulds
made of glass - fiber reinforced plastics.
Resin-coated & plastic -lined
surfaces are most suitable for producing smooth concrete faces, while mould
& made of plastics are good for producing patterned concrete.
a) Plywood
located with resin or synthetic resing produce a smooth & dense concrete
surface. As the mould has to be assembled from individual smaller panels,
however
the joints produce visible marks on the exposed
concrete faces. concrete instead of oil. Colurless mould release
pastes
(grease) used which do not cause any staining of concrete.
b) Moulds
lined with plastic sheeting : The sheets of plastic are smooth & are not
difficult to fix to moulds. Difficulties are arise only when heat treatment is
applied as adhesive used for fixing the sheeting lose their adhesive action at
elevated temperature.
Glass
fibre - reinforced moulds are very suitable for producing patterned surfaces as
this material can be shaped into a almost any classic patter by casting or
spraying it on to suitable Negative for the moulds too it is advisable to those
mould oils or pastes as
d) Other patterns can be produced by lining the
moulds with crude rubber or corrugated steel sheet or using rough faced timber
moulds, or placing gravel on the bottom.
surface
finish may be applied either:-
a) To the freshly cast concrete while it is
still wet or
b) to the
hardened concrete.
1 Mechanical
treatment of freshly placed concrete:-
It is usually applied to sand which panels cast with outs
deface upwards. The following
form of treatment are available.
v Screeding
the wet concrete with steel plates or cubes
v Float
finishing
v Treating
the surface with broons, brushes etc.
It is employed in industrial
building construction. It is simple to apply, it gives attractive appearance
but reduces the risk of cracking.
b) Mechanical
treatment of hardened concrete comprises:
v Scrubbing
or spraying to expose the aggregate
v Sand
blasting to expose the aggregate.
v Looking
(bush-hammering grinding etc).
The object of the scrubbed finish
is to expose the aggregate particles by playing a jet of water on the surface
or wire-brushing it at an appropriate length of tube after casting, whereby the
cement & sand particles are removed. This is really an intermediate
technique bet treatment of wet concrete & treatment applied after the
concrete has fully hardened.
Good results can be achieved by
the use of selting retarders which facilitate the removal of the fine particles
by spraying. This is done sometimes after concreting usually 1 to 2 hours,
depending on the prevailing temperature.
such process the 'O
crat' treatment has the object of increasing the strength of concrete
at the surface & at sametime making is resistant acid attack.
Facing & Coatings:-
In many cases it may be
advantages to apply a decorative kind /or protective coating to hardened
concrete. Attractive & durable surfaces can be obtained in this way.
E.g. with plastic coatings.
Erection :
An important requirement is that
erection can be carried out without scat folding or false work on this respect
it is advantageous to use vertical panels for low shed type building it the
joints can be sealed by workman standing on the roof: with high buildings light
suspended scat folds will be required for forming the joints. Alternatively,
the panels may be installed form inside the b/d with the aid of stacker trucks
or with winches & small trolleys.
The panels are suspended from the
cranes by means of cast-in attachments (lifting, loops, screw-threaded sockets
etc). some examples of such devices are illustrated.
Disuniting of Structures:-
The solution of problems
connected with the transportation and placing of structures demands as a rule
their disuniting into smaller members. One-by frames not exceeding 40 tons in
weight, may represent an exception, because the problem of their hoisting and
placing can be solved with the aid of modern available hoisting machines and
equipment.
In spite of this these frames are
frequently disunited as their corners or points of minimum moments into
members, to make the hoisting of these smaller members possible, using much
simpler equipments.
In general there is trend towards
the use of larger members. This is justified by more then one reason. One is
that the bearing of a certain moment can be solved more economically by using
one large girder instead of two or more smaller beams together having the same
bearing capacity indicates the moment bearing capacity of the girder. While the
enlargement of the cross section led to an 11-fold dead load, the moment
bearing capacity, increased 80-fold, However with regard to the load bearing
capacity, the moment-bearing capacity is not one unique Decisive factor because
the shear force that can be borne by a cross-section does not increase in the series
ratio as does one moment.
In addition the hoisting of one
larges member is as a rule, less expensive than that of two smaller members
having the same combined weight. It is a direct consequence of the following
circumstances: the assembling of the lifting tackle, the transfer of the
hoisting machine, the hoisting, placing and plumbing must be done for each
member separately, Independently of its weight.
into larger members means, lower
costs of hoisting and placing as well as saving in joining costs.
In the first case the expenses of
preparation and payments connected with the hire of the equipment may be
higher, but the work itself is much less.
Naturally, if plant
prefabrication is practiced, the greatest size of precast members is determined
by the transportation and shipping cost.
But demands are not unlimited
either so, members whose weight would exceed 60 tons cannot be found even in
structures of the largest power stations.
Now a
days, the hoisting capacity of derrick is 40 tons, while that of a pair of
twinned-mast cranes reaches 70 tons.
In this case the members should
be as large as possible within the limits of the available hoisting capacity.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.