The estimate has been prepared for the construction of an arch culvert of 3m span in 15 km-300 m on Lucknow -Daulatpur road.


Report on Estimate for Construction of a Culvert

 

The estimate has been prepared for the construction of an arch culvert of 3m span in

 

15 km-300 m on Lucknow -Daulatpur road. The road at this point is flooded almost every year during the rainy reason, causing flood and damages in the area. During the last

 

inspection the Executive Engineer has asked to prepare an estimate and this estimate has been prepared in compliance of E.E's letter no ………….dated …………….. the cost of

construction will be met from 50 civil work special repairs.

 

The culvert has been designed for I.R.A Class a loading. The catchment area has been determined from the 2.5 cm (1?) map of the area, which comes to 1200 acres, and the water way has been calculated by the Talbot formula a -cA 3 4 , where a = waterway in sq. ft , a=

Catchment area in acres, and c= constant and has been taken as 0.2. All calculation and design have been enclosed with the estimate.

 

The soil has been tested and has been found to be good, and ordinary spread foundation will be sufficient. The foundation shall be of cement concrete 1:4:8 and abutments, wing walls and parapets shall be of brick masonary in 1:5 cement mortar, the arch work shall be of brick masonry in 1:3 cement mortar. Exposed surfaces shall be cement pointed 1:2. all works shall be as per detailed P.W.D Specifications. The estimate has been prepared at P.W.D Schedule of Rates.

 

A statement of materials, cement, bricks, coal, etc., required for the construction , has been enclosed with he estimate. The work shall be executed on contract by inviting tenders and the work shall be started after the rainy season and shall be completed within four month's time.

 

The  estimate  amounting  to  Rs.  15,000.00  is  submitted  for  sanction  and  allotment of fund.

 

Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Estimation and Quantity Surveying : Report Preparation : Report on Estimate for Construction of a Culvert |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2024 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.