Relating
Cost and Schedule Information
The previous sections focused upon the
identification of the budgetary and schedule status of projects. Actual
projects involve a complex inter-relationship between time and cost. As
projects proceed, delays influence costs and budgetary problems may in turn
require adjustments to activity schedules. Trade-offs between time and costs
were discussed in Section 10.9 in the context of project planning in which
additional resources applied to a project activity might result in a shorter
duration but higher costs. Unanticipated events might result in increases in
both time and cost to complete an activity. For example, excavation problems
may easily lead to much lower than anticipated productivity on activities
requiring digging.
While project managers implicitly recognize the
inter-play between time and cost on projects, it is rare to find effective
project control systems which include both elements. Usually, project costs and
schedules are recorded and reported by separate application programs. Project
managers must then perform the tedious task of relating the two sets of
information.
The difficulty of integrating schedule and cost information
stems primarily from the level of detail required for effective integration.
Usually, a single project activity will involve numerous cost account categories.
For example, an activity for the preparation of a foundation would involve
laborers, cement workers, concrete forms, concrete, reinforcement,
transportation of materials and other resources. Even a more disaggregated
activity definition such as erection of foundation forms would involve numerous
resources such as forms, nails, carpenters, laborers, and material
transportation. Again, different cost accounts would normally be used to record
these various resources. Similarly, numerous activities might involve expenses associated
with particular cost accounts. For example, a particular material such as
standard piping might be used in numerous different schedule activities. To
integrate cost and schedule information, the disaggregated charges for specific
activities and specific cost accounts must be the basis of analysis.
A straightforward means of relating time and cost
information is to define individual work elements representing the resources in
a particular cost category associated with a particular project activity. Work
elements would represent an element in a two-dimensional matrix of activities
and cost accounts as illustrated in Figure 3-6. A numbering or identifying
system for work elements would include both the relevant cost account and the
associated activity. In some cases, it might also be desirable to identify work
elements by the responsible organization or individual. In this case, a three
dimensional representation of work elements is required, with the third
dimension corresponding to responsible individuals. More generally, modern
computerized databases can accommodate a flexible structure of data
representation to support aggregation with respect to numerous different
perspectives; this type of system will be discussed in Chapter 5.
With this
organization of information, a number of management reports or views could be
generated. In particular, the costs associated with specific activities could
be obtained as the sum of the work elements appearing in any row in Figure 3-6.
These costs could be used to evaluate alternate technologies to accomplish
particular activities or to derive the expected project cash flow over time as
the schedule changes. From a management perspective, problems developing from
particular activities could be rapidly identified since costs would be
accumulated at such a disaggregated level. As a result, project control becomes
at once more precise and detailed
Unfortunately, the development and maintenance of
a work element database can represent a large data collection and organization
effort. As noted earlier, four hundred separate cost accounts and four hundred
activities would not be unusual for a construction project. The result would be
up to 400x400 = 160,000 separate work elements. Of course, not all activities
involve each cost account. However, even a density of two percent (so that each
activity would have eight cost accounts and each account would have eight
associated activities on the average) would involve nearly thirteen thousand
work elements. Initially preparing this database represents a considerable
burden, but it is also the case that project bookkeepers must record project
events within each of these various work elements. Implementations of the
"work element" project control systems have typically fondered on the
burden of data collection, storage and book-keeping.
Until data collection is better automated, the use
of work elements to control activities in large projects is likely to be
difficult to implement. However, certain segments of project activities can
profit tremendously from this type of organization. In particular, material
requirements can be tracked in this fashion. Materials involve only a subset of
all cost accounts and project activities, so the burden of data collection and
control is much smaller than for an entire system. Moreover, the benefits from
integration of schedule and cost information are particularly noticeable in
materials control since delivery schedules are directly affected and bulk order
discounts might be identified. Consequently, materials control systems can
reasonably encompass a "work element" accounting system.
In the absence
of a work element accounting system, costs associated with particular
activities are usually estimated by summing expenses in all cost accounts
directly related to an activity plus a proportion of expenses in cost accounts
used jointly by two or more activities. The basis of cost allocation would
typically be the level of effort or resource required by the different
activities. For example, costs associated with supervision might be allocated
to different concreting activities on the basis of the amount of work (measured
in cubic yards of concrete) in the different activities. With these
allocations, cost estimates for particular work activities can be obtained.
Related Topics
Privacy Policy, Terms and Conditions, DMCA Policy and Compliant
Copyright © 2018-2023 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.