Primary Sedimentation. Detention Period - 12 to 36 hours.

Sewage Treatment: Septic Tank

Primary Sedimentation

Detention Period - 12 to 36 hours

Works on the principle of anaerobic decomposition

Rectangular type - constructed below GL

Removes about 60 to 70 % dissolved matter from it.

 

Design Considerations

 

Number of souls per house hold: 5

 

Number of fixture  per house hold: 1

% of unit discharge simultaneously : 60

Discharge from each sedimentation : 1 m2/10Lpm of peak discharge

Minimum depth for sedimentation : 30cm

 