Home | | Railways and Airports and Harbour Engineering | Methods of Railway Tunnelling

Chapter: Civil : Railway Airport Harbour Engineering : Railway Engineering : Railway Tunnelling

Methods of Railway Tunnelling

There are various methods of tunnelling. The selection of a method depends upon the size of the bore, the condition of the ground, the equipment available, and the extent to which timbering is required. Tunnelling may be basically divided into two main groups. (a) Tunnelling in hard rocks (b) Tunnelling in soft rocks

Methods of Tunnelling

 

There are various methods of tunnelling. The selection of a method depends upon the size of the bore, the condition of the ground, the equipment available, and the extent to which timbering is required. Tunnelling may be basically divided into two main groups.

 

(a)  Tunnelling in hard rocks

(b) Tunnelling in soft rocks

 

 

 

These are described in detail in the subsequent sections. Tunnelling through water-bearing strata and compressed air tunnelling are discussed subsequently.

 

1 Tunnelling in Hard Rocks

 

The following methods are generally employed for tunnelling in hard rocks.

 

Full face method

 

The full face method is normally selected for small tunnels whose dimensions do not exceed 3 m. In this method, the full face or the entire facade of the tunnel is tackled at the same time. Vertical columns are erected at the face of the tunnel and a large number of drills mounted or fixed on these columns at a suitable height as shown in Fig. 3.2. A series of holes measuring 10 mm to 40 mm in diameter with about 1200 mm centre-to-centre distance are then drilled into the rock, preferably in two rows. These holes are charged with explosives and ignited. Next the muck is removed before repeating the process of drilling holes.



Advantages

 

(a)  Since an entire section of the tunnel is tackled at one time, the method is completed expeditiously.

 

(b) Mucking tracks, which are tracks used for collecting muck, can be laid on the tunnel floor and extended as the work progresses.

 

(c)  With the development of the 'jumbo' or drill carriage, this method can be used for larger tunnels too.

 

Disadvantages

 

(a)  The method requires heavy mechanical equipment.

 

(b) It is not very suitable for unstable rocks.

 

(c)  It can normally be adopted for small tunnels only.

 

Heading and bench method

 

In this method, the heading (top or upper half) of the tunnel is bored first and then the bench (bottom or lower half) follows. The heading portion lies about 3.70 m to 4.60 m ahead of the bench portion (Fig. 30.3). In hard rock, the drill holes for the bench are driven at the same time as the removal of the muck. The hard rock permits the roof to stay in place without supports.

 


 

Advantages

 

(a)  The work of drilling of holes for the explosives and the removal of muck can progress simultaneously.

 

(b) This method requires the use of lower quantities of gunpowder than the full face method.

 

Drift method

 

A drift is a small tunnel measuring 3 m × 3 m, which is driven into the rock and whose section is widened in subsequent processes till it equates that of the tunnel. A number of drill holes are provided all around the drift and these are filled up with explosives and ignited so that the size of the drift expands to become equal to the required cross section of the tunnel.

 

The position of the drift depends upon local conditions; it may be in the centre, top, bottom, or side as shown in Fig. 30.4. Field experience has shown that the central drift is the best choice, as it offers better ventilation and requires lower quantities of explosives. The side drift, however, has the advantage that it permits the use of timber to support the roof.

 

Advantages

 

(a)  If the quality of the rock is bad or if it contains excessive water, this is detected in advance and corrective measures can then be taken in time.

 

(b) A drift assists in the ventilation of tunnels.

 

(c)  The quantity of explosives required is less.

 

(d) A side drift allows the use of timber to support the roof.

 

Disadvantages

 

(a)  It is a time-consuming process, as the excavation of the main tunnel gets delayed till the drift is completed.

(b) The cost of drilling and removing the muck from the drift is high, as the work has to be done using manually operated power-driven equipment.

 


 

Pilot tunnel method

 

This method normally involves the digging of two tunnels, namely, a pilot tunnel and a main tunnel. The cross section of the pilot tunnel usually measures about 2.4 m × 2.4 m. The pilot tunnel is driven parallel to the main tunnel and connected to the centre line of the main tunnel with cross cuts at many points. The main tunnel is then excavated from a number of points. The pilot tunnel offers the following advantages.

 


 

(a)  It helps in removing the muck from the main tunnel quickly.

 

(b) It helps in providing proper ventilation and lighting in the main tunnel. The method, however, requires the construction of an additional tunnel and therefore the time and cost of construction are higher as compared to the methods described before.

 

Perimeter method of tunnelling

 

In this method, the excavation is carried out along the perimeter or periphery of the section. The method is also known as the German method.

 

2 Tunnelling in Soft Ground or Soft Rock

 

Tunnelling in soft ground or soft rock is a specialized job. It does not involve the use of explosives and the requisite excavation work is done using hard tools such as pickaxes and shovels. In recent times, compressed air has also been used for this purpose. During excavation, the rail requires support at the sidewalls and the roofs depending upon the type of soil. The support could be provided in the form of timber or steel plates or other similar material. The various operations involved in soft rock tunnelling are as follows.

 

(a)  Excavation or mining

 

(b) Removal of excavated material

 

(c)  Scaffolding and shuttering

 

(d) Lining of tunnel surface

 

The nature of the ground is the most important factor in deciding the method to be used for tunnelling. The types of ground which are generally encountered in the field are detailed in Table 30.3.

 

Table 30.3   Types of grounds



In the case of soft rock, the selection of the method of tunnelling depends upon the following important factors.

 

(a)  Nature of ground

 

(b) Size of tunnel

 

(c)  Equipment available

 

(d) Sequence of operations

 

Some of the important methods of tunnelling in soft rock are described in the following sections.

 

Forepoling method

 

Forepoling is an old method of tunnelling through soft ground. In this method, a frame is prepared in the shape of the letter A, placed near the face of the tunnel, and covered with suitable planks. Poles are then inserted at the top of the frame up to a viable depth. The excavation is carried out below these poles, which are supported by vertical posts. The excavation is carried out on the sides and the excavated portion is suitably supported by timber. The entire section of the tunnel is covered thus. The process is repeated as the work progresses.

 


 

Forepoling is a slow and tedious process and requires skilled manpower and strict supervision. The method has to be meticulously repeated in sequence and there is no short cut for the same.

 

Linear plate method

 

In the linear plate method (Fig. 30.7), timber is replaced by standard size pressed steel plates. The use of pressed steel plates is a recent development. The method has the following advantages.


 

(a)  The linear plates are light and can be handled easily.

 

(b) The number of joints is less, as the linear plates are bigger in size, and as

 

such the maintenance cost is low.

 

(a)  The steel plates are fireproof and can be safely used while working in compressed air condition.

 

(d) The necessary work can be done by semi-skilled staff.

 

(e)  There is considerable saving in terms of the excavation and concrete required.

 

Needle beam method

 

The needle beam method (Fig. 30.8) is adopted in terrains where the soil permits the roof of the tunnel section to stand without support for a few minutes. In this method, a small drift is prepared for inserting a needle beam consisting of two rail steel (RS) joists or I sections and is bolted together with a wooden block in the centre. The roof is supported on laggings carried on the wooden beam. The needle beam is placed horizontally with its front end supported on the drift and the rear end supported on a vertical post resting on the lining of the tunnel. Jacks are fixed on the needle beam and the tunnel section is excavated by suitably incorporating timber. This method of tunnelling is more economical compared to other methods.



American method

 

In this method (Fig. 30.9), a drift is driven into the top of the tunnel. The drift is supported by laggings, caps, and two vertical posts. The sides of the drift are then widened and additional support is provided using timber planks and struts. The process of widening is continued till it reaches the springing level. Wall plates are fixed at the springing level, which in turn are supported by vertical posts. The vertical posts now occupy the entire roof level. The posts supporting the drift can then be removed and tunnelling work continued further in a similar manner.

 

English method

 

This method is similar to the American method except that the roof load is supported by underpinning instead of using vertical posts. A drift is driven into the top of the tunnel about 5 m ahead of the existing arch lining. The drift is subsequently widened on both sides and supported by crown bars and posts. The work is carried on till the springing level is reached. The sill is then extended across the tunnel and the extended piece is supported by underpinning. This method requires good quality timber as well as simultaneous and frequent shifting from place to place.

 


 

Austrian method

 

This method is used for long tunnels, particularly those at great depths, where the walls of the excavation may yield under the weight of the cover. It involves excavating the whole section for a short length and furnishing with sidewalls and an arch.

 

Belgian method

 

This method is particularly suitable for areas where the height of the overburden is less and the surface is not to be disturbed. In this case, the heading is excavated first and supported by crown bar posts and laggings. The sides are excavated next and supported by crown bars and posts. Finally, the work of lining the arch is carried out and further excavation is done.

 

3 Tunnelling Through Water-bearing Strata

 

Tunnelling through subaqueous or water-bearing strata is quite a different job. Shield tunnelling is generally preferred in such cases. A shield is a movable frame that is used to support the face of a tunnel. The tunnel is excavated and lined under the protection of the shield.

 

A shield is a device meant for excavation that is to be carried out beneath water-bearing strata. It basically consists of a cutting edge, a skin plate in the form of a shell structure, and a hood of jacks, ring girders, stiffening steel plates, ports as well as port doors, and a tail. The various methods of shield tunnelling through different types of soils are enumerated in Table 30.4.

Table 30.4   Methods of shield tunnelling in different soils


Tunnels constructed using the shield method usually have a circular section because of the following considerations.

 

(a)  The rotation of the shield is easy in a circular section.

 

(b) It grants protection to the primary lining.

 

(c)  The circular section provides the maximum cross-sectional area with the smallest perimeter.

 

(d) The circular section is ideally suited to resist the semi-fluid pressure exerted by the soft ground.

 

 

4 Compressed Air Tunnelling

 

This method is possibly the most modern method of tunnelling. The compressed air, which has a pressure of about 1 kg/cm2, is forced into the enclosed space within the tunnel so that the sides and top of the tunnel do not collapse and remain in their position. The equipment for tunnelling consists of a bulk head, which is an airtight diaphragm with an airlock. The airlock is an airtight cylindrical steel chamber with a door at each end opening inwards.

 

Tunnelling by means of compressed air is quite a difficult process because of the following reasons.

 

(a)  The pressure inside the earth varies from the bottom to the top of the tunnel.

 

(b) It is not possible to ascertain the pressure on the floor of the tunnel as it depends upon the nature of the strata.

 

(c)  The pressure varies from strata to strata depending upon the moisture content, which is difficult to ascertain.

 

(d) The compressed air normally escapes through the pores and the air pressure diminishes continuously. The application of air pressure has to be varied from time to time in order to achieve a balanced value. The determination of this value depends more on experience than on technical considerations.

 

Study Material, Lecturing Notes, Assignment, Reference, Wiki description explanation, brief detail
Civil : Railway Airport Harbour Engineering : Railway Engineering : Railway Tunnelling : Methods of Railway Tunnelling |


Privacy Policy, Terms and Conditions, DMCA Policy and Compliant

Copyright © 2018-2024 BrainKart.com; All Rights Reserved. Developed by Therithal info, Chennai.